88433RECLASSIFY CONTINGENCY20/07/2021 06:43:39 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 0640 hrs 20/07/2021 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
88432PRICES SUBJECT TO REVIEW20/07/2021 06:40:16 AM

[EventId:202107200645_review] Prices for interval 20-Jul-2021 06:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0640 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88431PRICES SUBJECT TO REVIEW20/07/2021 06:35:12 AM

[EventId:202107200640_review] Prices for interval 20-Jul-2021 06:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0635 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88430PRICES SUBJECT TO REVIEW20/07/2021 06:30:21 AM

[EventId:202107200635_review] Prices for interval 20-Jul-2021 06:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0630 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88429PRICES SUBJECT TO REVIEW20/07/2021 06:25:18 AM

[EventId:202107200630_review] Prices for interval 20-Jul-2021 06:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0625 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88428PRICES SUBJECT TO REVIEW20/07/2021 06:20:20 AM

[EventId:202107200625_review] Prices for interval 20-Jul-2021 06:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0620 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88427PRICES SUBJECT TO REVIEW20/07/2021 06:15:24 AM

[EventId:202107200620_review] Prices for interval 20-Jul-2021 06:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0615 hrs on 20 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 20-Jul-2021 06:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88426RESERVE NOTICE19/07/2021 08:52:40 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 21/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 conditions in the NSW region advised in AEMO Electricity Market Notice No. 88423 have been updated at 2000 hrs 19/07/2021 to the following:

1. From 1730 hrs 21/07/2021 to 1930 hrs 21/07/2021.
The forecast capacity reserve requirement is 1421 MW.
The minimum capacity reserve available is 1129 MW.

2. From 0700 hrs 22/07/2021 to 0900 hrs 22/07/2021.
The forecast capacity reserve requirement is 1401 MW.
The minimum capacity reserve available is 632 MW.

3. From 1800 hrs 22/07/2021 to 1900 hrs 22/07/2021.
The forecast capacity reserve requirement is 1164 MW.
The minimum capacity reserve available is 1007 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
88425RESERVE NOTICE19/07/2021 05:56:48 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 20/07/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs 20/07/2021 to 1900 hrs 20/07/2021
The forecast capacity reserve requirement is 1084 MW.
The minimum capacity reserve available is 1077 MW.

Manager NEM Real Time Operations