Market Notices

84823PRICES SUBJECT TO REVIEW27/04/2021 10:15:18 AM

[EventId:202104271020_review] Prices for interval 27-Apr-2021 10:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 10:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84822PRICES SUBJECT TO REVIEW27/04/2021 10:10:12 AM

[EventId:202104271015_review] Prices for interval 27-Apr-2021 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84821PRICES SUBJECT TO REVIEW27/04/2021 10:05:12 AM

[EventId:202104271010_review] Prices for interval 27-Apr-2021 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84820PRICES SUBJECT TO REVIEW27/04/2021 10:00:16 AM

[EventId:202104271005_review] Prices for interval 27-Apr-2021 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84819GENERAL NOTICE27/04/2021 09:57:44 AM

Planned outage of Heywood to Mortlake 500kV line Circuit Breaker (213) in the Victoria region on 2/05/2021

AEMO ELECTRICITY MARKET NOTICE

The Heywood Mortlake power station No. 2 line No. 2 bus 500kV Circuit Breaker (213) in the Victoria (VIC) region is planned to be out of service from 0700 hrs to 1900 hrs on 2/05/2021.

A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM. If separation occurs, load may be interrupted due to the operation of the Automatic Under Frequency Load Shedding (AUFLS) scheme in SA.

The credible separation contingency is managed as follows:

-When power transfer is from SA to Victoria, contingency lower FCAS will be sourced from SA.
-When power transfer is from Victoria to SA, due to the 47-52Hz island separation frequency band advised by the SA jurisdiction, contingency raise FCAS is not sourced in SA and the AUFLS scheme may respond to low frequency events.
-Power transfer will be restricted on Victoria - South Australia interconnector (Heywood interconnector) to manage system security following the loss of the next contingency.

Forecast capacity reserves in the SA region are currently sufficient to meet electricity demand during the planned outage.

The following constraint sets have been invoked for this outage:

F-I-HYSE
I-VS_050
S-X_BC_CP
V-HYCB_210_213

Refer AEMO Network Outage Schedule (NOS) for further details.

Diyoni Hoole
AEMO Operations
84818PRICES SUBJECT TO REVIEW27/04/2021 09:55:17 AM

[EventId:202104271000_review] Prices for interval 27-Apr-2021 10:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0955 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 10:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84817PRICES SUBJECT TO REVIEW27/04/2021 09:50:15 AM

[EventId:202104270955_review] Prices for interval 27-Apr-2021 09:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0950 hrs on 27 April 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 27-Apr-2021 09:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
84816PRICES UNCHANGED27/04/2021 09:37:23 AM

[EventId:202104270910_confirmed] Prices for interval 27-Apr-2021 09:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0930 hrs on 27 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 27-Apr-2021 09:10.

In accordance with Market Notice 84802 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
84815PRICES UNCHANGED27/04/2021 09:36:11 AM

[EventId:202104270930_confirmed] Prices for interval 27-Apr-2021 09:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0930 hrs on 27 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 27-Apr-2021 09:30.

In accordance with Market Notice 84810 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm