92132MARKET SYSTEMS03/11/2021 01:45:23 PM

CHG0070905 : MSATS V47.0 & B2B schema r41 Production Release

Change Number: CHG0070905

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: MSATS V47.0 & B2B schema r41 Production Release.

Change Start Date & Time: 09/11/2021 17:30:00 AEST

Change End Date & Time: 09/11/2021 19:30:00 AEST

Outage Start Date & Time: 09/11/2021 17:30:00 AEST


Outage End Date & Time: 09/11/2021 19:30:00 AEST

Environment: Production

Participant Impact and Requirements: This outage is to allow the deployment of a MSATS V47.0 & B2B schema r41 release into Production .

There will be no access to the Production MSATS system for the duration of the outage . Please access outside these hours.

All participants that are currently on the Superseded version r36 will be moved to r38 post release.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
92131GENERAL NOTICE03/11/2021 12:57:40 PM

Planned outage of Tungkillo - Tailem Bend 275 kV line in the SA region from 12/11/2021 to 13/11/2021

AEMO ELECTRICITY MARKET NOTICE

The Tungkillo - Tailem Bend 275 kV line in South Australia (SA) region is planned to be out of service from 12/11/2021 2030 hrs to 13/11/2021 0430 hrs.

During this outage, SA will remain connected to the rest of the NEM via the Tailem Bend - Cherry Gardens 275 kV line and the 132kV network.

A credible contingency event on the Tailem Bend - Cherry Gardens 275 kV line during this planned outage will sever the 275kV connections between Victoria and SA. If SA remains connected to Victoria via the 132kV network only, this will pose a system security issue.

If the above credible contingencies occur, AEMO will take all necessary steps as outlined in Section 3.1 of SO_OP_3715 Power System Security Guideline to separate the 132kV network and therefore manage an orderly separation of SA from the rest of the NEM.



Ayesha Ashfaq
AEMO Operations
92130MARKET SYSTEMS03/11/2021 09:53:34 AM

CHG0070863 | Completed | Production | Verification test of new data interchange FTP servers will occur between 09:00 and 11:00 AEST

Change Number: CHG0070863

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: EMMS - Data Interchange

Change Title: Verification test of new data interchange FTP servers will occur between 09:00 and 11:00 AEST

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
92125RESERVE NOTICE02/11/2021 06:00:54 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/11/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 92116 is cancelled at 1800 hrs 02/11/2021


Manager NEM Real Time Operations
92124RESERVE NOTICE02/11/2021 05:57:19 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/11/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 92115 is cancelled at 1800 hrs 02/11/2021

Manager NEM Real Time Operations
92118MARKET SYSTEMS02/11/2021 03:43:27 PM

CHG0070905 | Production | MSATS V47.0 & B2B schema r41 Production Release.

Change Number CHG0070905
Environment Production
Change Type Normal
Risk High
Service/Component MSATS - Business to Business data exchange
Change Title MSATS V47.0 & B2B schema r41 Production Release.
Change Start Date & Time 09/11/2021 17:30:00 Change End Date & Time 09/11/2021 19:30:00
Outage Start Date & Time 09/11/2021 17:30:00 Outage End Date & Time 09/11/2021 19:30:00
Change Description/ Participant Impact and Requirements
This outage is to allow the deployment of a MSATS V47.0 & B2B schema r41 release into Production .
There will be no access to the Production MSATS system for the duration of the outage . Please access outside these hours.
All participants that are currently on the Superseded version r36 will be moved to r38 post release.

Support Information
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
.
92117RESERVE NOTICE02/11/2021 02:41:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 08/11/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 92108 has been updated at 1400 hrs to the following:

[1.] From 1730 hrs 08/11/2021 to 1900 hrs 08/11/2021.
The forecast capacity reserve requirement is 918 MW.
The minimum capacity reserve available is 771 MW.

[2.] From 1730 hrs 09/11/2021 to 1930 hrs 09/11/2021.
The forecast capacity reserve requirement is 1077 MW.
The minimum capacity reserve available is 849 MW.

AEMO Operations
92116RESERVE NOTICE02/11/2021 01:06:19 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/11/2021

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/11/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0900 hrs 03/11/2021 to 1000 hrs 03/11/2021.
The forecast capacity reserve requirement is 361 MW.
The minimum capacity reserve available is 283 MW.


Manager NEM Real Time Operations
92115RESERVE NOTICE02/11/2021 01:07:07 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/11/2021

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/11/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0830 hrs 03/11/2021 to 0900 hrs 03/11/2021.
The forecast capacity reserve requirement is 265 MW.
The minimum capacity reserve available is 197 MW.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 02/11/2021.