Market Notices

116374MARKET SYSTEMS29/04/2024 03:35:35 PM

CHG0088931 | Completed | Production | Planned System Maintenance activity.

Change Number: CHG0088931

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: EMS NEM - Network Outage Scheduler (NOS)

Change Title: Planned System Maintenance activity.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
116370MARKET INTERVENTION29/04/2024 02:46:55 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116368

The synchronous generating units currently expected to be synchronised in SA from 0800 hrs 30/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 29/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116369NON-CONFORMANCE29/04/2024 01:05:16 PM

NON-CONFORMANCE Region VIC1 Monday, 29 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 29 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JLB01
Duration: 29/04/2024 13:00 to 29/04/2024 13:05
Amount: 35 MW
Constraint: NC-V_JLB01

Auto-generated on behalf of Manager NEM Real Time Operations
     
116368MARKET INTERVENTION29/04/2024 12:48:10 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 30/04/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116367MARKET SYSTEMS29/04/2024 10:36:02 AM

CHG0089027 | Cancelled | Pre-Production | Pre-Prod eMDM May Maintenance Release

Change Number: CHG0089027

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal

Service/ Component: MDM - Meter Data Management

Change Title: Pre-Prod eMDM May Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600

     
116366RECLASSIFY CONTINGENCY29/04/2024 06:29:49 AM

Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Cancellation time: 29/04/2024 06:29

Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 116365

Auto-generated on behalf of Manager NEM Real Time Operations
     
116365RECLASSIFY CONTINGENCY29/04/2024 05:28:35 AM

Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Duration: 29/04/2024 05:28 until further notice

Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
116364MARKET INTERVENTION28/04/2024 05:00:44 PM

Cancellation - Possible intervention to manage power system security in SA region 28/04/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region 28/04/2024

Refer Market Notice 116361

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1700 hrs 28/04/2024.

Manager NEM Real Time Operations
     
116363MARKET INTERVENTION28/04/2024 03:30:28 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/04/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/04/2024

Refer Market Notice 116353

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs 28/04/2024

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm