PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 27/10/2021
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 91961 is cancelled at 1515 hrs 26/10/2021.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 27/10/2021
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 91960 is cancelled at 1515 hrs 26/10/2021.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/10/2021
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/10/2021
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1800 hrs 26/10/2021 to 1900 hrs 26/10/2021.
The forecast capacity reserve requirement is 1186 MW.
The minimum capacity reserve available is 1133 MW.
Manager NEM Real Time Operations
CHG0070863 | Production | Verification test of new data interchange FTP servers will occur between 09:00 and 11:00 AEST
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Interchange
Change Title: Verification test of new data interchange FTP servers will occur between 09:00 and 11:00 AEST
Change Start Date & Time: 03/11/2021 09:00:00 AEST
Change End Date & Time: 03/11/2021 11:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: During this window, there could be a delay of 30 seconds for non-critical FTP report delivery. Bids will continue to be processed normally.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
CHG0070639 | Production | MSATS Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution (CATS)
Change Title: MSATS Production Release
Change Start Date & Time: 27/10/2021 17:30:00 AEST
Change End Date & Time: 28/10/2021 16:00:00 AEST
Outage Start Date & Time: 27/10/2021 17:30:00 AEST
Outage End Date & Time: 27/10/2021 19:30:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage.
NMI Discovery will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/10/2021
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 91959 is cancelled at 1355 hrs 26/10/2021
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV
Duration: 26/10/2021 13:17 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 27/10/2021
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1930 hrs 27/10/2021 to 2000 hrs 27/10/2021.
The forecast capacity reserve requirement is 375 MW.
The minimum capacity reserve available is 334 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 27/10/2021
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
[1.] From 1730 hrs 27/10/2021 to 1800 hrs 27/10/2021.
The forecast capacity reserve requirement is 321 MW.
The minimum capacity reserve available is 249 MW.
[2.] From 1830 hrs 27/10/2021 to 1930 hrs 27/10/2021.
The forecast capacity reserve requirement is 315 MW.
The minimum capacity reserve available is 254 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1530 hrs on 26/10/2021
Manager NEM Real Time Operations