Filter by category
Filter by Date
Cancellation of the Reclassification of a Non Credible Contingency event to a Credible Event - Kareeya Power Station - Qld Region
Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event in the Qld region.
AEMO considers the trip of the Kareeya Power Station is no longer reasonably possible. Accordingly, its classification has reverted to a non-credible contingency event.
Region: QLD
Elements: Kareeya Power Station
Cancellation time: 0700 hrs 09/09/2021
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 82304
Manager NEM Real Time Operations
UPDATE : CHG0069699 : Software Upgrade of MarketNet F5 load-balancers in Norwest
Market Notice
Change Number: CHG0069699
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Software Upgrade of MarketNet F5 load-balancers in Norwest
Change Start Date & Time: 15/09/2021 06:00:00 AEST
Change End Date & Time: 15/09/2021 18:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
Planned maintenance affecting the AEMO Market Network.
Environment: Production
Participant Impact and Requirements:
Planned maintenance will be conducted on the 15th of September 2021, between 06:00AM and 06:00PM AEST on the core network infrastructure within the AEMO Market Network in Sydney.
No outage or impact is expected, however AEMO recommends that all market participants with site to site VPN connections currently connected via Sydney, to switch these connections to the Brisbane site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Brisbane site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0069318 : e-Hub production cutover of existing keystore
Change Number: CHG0069318
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: e-Hub production cutover of existing keystore
Change Start Date & Time: 19/09/2021 10:00:00 AEST
Change End Date & Time: 19/09/2021 12:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
Please note the X.509 digital public certificate securing traffic from the following endpoints is being renewed
Environment: Production
Participant Impact and Requirements:
Participants connecting to these endpoints or receiving requests from AEMO's eHub B2B or FRC Gas Hub platforms and have certificate pinning / fingerprinting in place will notice a change in the certificate fingerprint and may need to update their systems accordingly.
https://apis.prod.aemo.com.au:9319
https://apis.prod.marketnet.net.au:9319
https://hub.aemo.com.au:5319
https://hub.marketnet.net.au:5319
https://prod.frchub.net:5319
Certificates can be downloaded from https://dev.aemo.com.au/tls-certificates#certificate-downloads
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0069807 : 5MS - Retail eMDM Production Defect Deployment
Change Number: CHG0069807
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: 5MS - Retail eMDM Production Defect Deployment
Change Start Date & Time: 15/09/2021 17:30:00 AEST
Change End Date & Time: 16/09/2021 16:00:00 AEST
Outage Start Date & Time: 15/09/2021 17:30:00 AEST
Outage End Date & Time: 15/09/2021 19:30:00 AEST
Change Description:
The next version of the 5MS Retail MSATS solution will be deployed to the AEMO Production environment which requires an Outage as specified in this notice.
Environment: Production
Participant Impact and Requirements:
Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 14/09/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 14/09/2021.
The forecast capacity reserve requirement is 741 MW.
The minimum capacity reserve available is 710 MW.
AEMO Operations
CHG0069694 : Planned System Maintenance activity
Change Number: CHG0069694
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity
Change Start Date & Time: 15/09/2021 11:00:00 AEST
Change End Date & Time: 15/09/2021 11:40:00 AEST
Outage Start Date & Time: 15/09/2021 11:10:00 AEST
Outage End Date & Time: 15/09/2021 11:20:00 AEST
Change Description:
Planned System Maintenance activity.
Environment: Production
Participant Impact and Requirements:
Network Outage Schedular (NOS) will be out of service during the maintenance activity. Users who are already logged in to NOS during the outage will not be able to use NOS and will require log back in once the outage is completed.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0069699 : Software Upgrade of MarketNet F5 load-balancers in Norwest
Change Number: CHG0069699
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Software Upgrade of MarketNet F5 load-balancers in Norwest
Change Start Date & Time: 15/09/2021 06:00:00 AEST
Change End Date & Time: 15/09/2021 18:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
Planned maintenance affecting the AEMO Market Network.
Environment: Production
Participant Impact and Requirements:
Planned maintenance will be conducted on the 8th of September 2021, between 06:00AM and 06:00PM AEST on the core network infrastructure within the AEMO Market Network in Sydney.
No outage or impact is expected, however AEMO recommends that all market participants with site to site VPN connections currently connected via Sydney, to switch these connections to the Brisbane site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Brisbane site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation - Possible intervention to manage power system security in South Australia (SA) region
Cancellation - Possible intervention to manage power system security in SA region
Refer Market Notice 90269
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1430 hrs 08/09/2021
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 8 September 2021
NON-CONFORMANCE NSW1 Region Wednesday, 8 September 2021
AEMO declared a schedule generating unit non-conforming
Unit: DARLSF1
Duration: 08/09/2021 08:25 to 08/09/2021 09:10
Amount: 49 MW
Constraint: NC-N_DARLSF1
Auto-generated on behalf of Manager NEM Real Time Operations