Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units expected to be synchronised in SA from 1000 hrs 08/06/2021 to 1500 hrs 08/06/2021 in Pre-dispatch published at 1600 hrs 07/06/2021 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 1800 hrs 07/06/2021, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 1453 hrs 07/06/2021 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/06/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 10/06/2021 to 1900 hrs 10/06/2021.
The forecast capacity reserve requirement is 1414 MW.
The minimum capacity reserve available is 1218 MW.
Operations Planning, AEMO
STPASA - Update Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 10/06/2021
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 86701 has been updated at 1400 hrs 07/06/2021 to the following:
[1.] From 1730 hrs 10/06/2021 to 2030 hrs 10/06/2021.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 580 MW.
Operations Planning, AEMO
CCHG0064858 - Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM) - CANCELLED
Market Notice
Change Number: CHG0064858
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Expedited
Service/ Component: Declared Wholesale Gas Market
Change Title: Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 07/06/2021 18:00:00 AEST
Change End Date & Time: 07/06/2021 21:00:00 AEST
Outage Start Date & Time: 07/06/2021 18:30:00 AEST
Outage End Date & Time: 07/06/2021 20:30:00 AEST
Change Description:
Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)
Environment: Production
Participant Impact and Requirements:
DWGM market system (Webexchanger and MIBB) outage from 18:00 to 20:30 AEST on 07/06/21 due to unplanned maintenance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0064858 - Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Number: CHG0064858
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Expedited
Service/ Component: Declared Wholesale Gas Market
Change Title: Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 07/06/2021 18:00:00 AEST
Change End Date & Time: 07/06/2021 21:00:00 AEST
Outage Start Date & Time: 07/06/2021 18:30:00 AEST
Outage End Date & Time: 07/06/2021 20:30:00 AEST
Change Description:
Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)
Environment: Production
Participant Impact and Requirements:
DWGM market system (Webexchanger and MIBB) outage from 18:00 to 20:30 AEST on 07/06/21 due to unplanned maintenance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202106071045_confirmed] Prices for interval 07-Jun-2021 10:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 7 June 2021
PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 10:45.
In accordance with Market Notice 86714 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202106071105_confirmed] Prices for interval 07-Jun-2021 11:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 7 June 2021
PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 11:05.
In accordance with Market Notice 86719 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202106071100_confirmed] Prices for interval 07-Jun-2021 11:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 7 June 2021
PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 11:00.
In accordance with Market Notice 86718 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.