Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event will be met from the time specified in this notice.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Duration: 08/08/2019 12:00 hrs until further notice
AEMO will take action to manage the power system for the impact of the protected event.
Constraint set(s) invoked: I-VS_250
Manager NEM Real Time Operations
Request for Generator Recall Information for 01/03/2019 for South Australia Region
Please provide Generator Recall Information for 01/03/2019 for South Australia Region, by 1800 hrs on 27/02/2019 via the Generator Recall communication system, in accordance with the SO_OP_3719 Procedure for Submitting Generator Outage Recall Information.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
Manager Operations Planning
Request for Generator Recall Information for 03/01/2019 for South Australia Region
Please provide Generator Recall Information for 03/01/2019, by 1000 hrs on 02/01/2019 via the Generator Recall communication system, in accordance with the SO_OP_3719 Procedure for Submitting Generator Outage Recall Information.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
Manager Operations Planning
Communication system and a procedure for Scheduled Generators to submit recall information
As a part of AEMO's summer readiness program, AEMO has established a communication system and an operating procedure for Scheduled Generators to submit recall information of their outages electronically to AEMO systems.
The operating procedure SO_OP_3719 - Procedure for Submitting Recall Information of Scheduled Generator Outages explains this process. It is available on AEMO website at:
http://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Security-and-reliability/Power-system-operation
Given that AEMO and participant systems are ready, commencing from Monday 29 January 2018, AEMO will use this new communication system and the procedure to obtain recall information of Scheduled Generator outages for the purposes of NER clause 4.8.5A for all regions except Tasmania.
Ken Harper
Group Manager Operational Support