128434SETTLEMENTS RESIDUE04/08/2025 08:00:21 PM

[EventId:202508042000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 August 2025 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 4 August 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 August 2025.

Refer to market notice: 128433

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2000 hrs on 4 August 2025.

This is an AEMO autogenerated Market Notice.
     
128433SETTLEMENTS RESIDUE04/08/2025 07:00:29 PM

[EventId:202508041900_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 August 2025 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 August 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 August 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1900 hrs on 4 August 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
128430RESERVE NOTICE04/08/2025 02:40:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.

AEMO Operations
     
128415NON-CONFORMANCE01/08/2025 02:40:13 PM

NON-CONFORMANCE Region NSW1 Friday, 1 August 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 1 August 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEVERSF1
Duration: 01/08/2025 14:25 to 01/08/2025 14:40
Amount: 26 MW
Constraint: NC-N_NEVERSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128410NON-CONFORMANCE31/07/2025 03:35:22 PM

NON-CONFORMANCE Region NSW1 Thursday, 31 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 31 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HUNTER1
Duration: 31/07/2025 15:05 to 31/07/2025 15:35
Amount: -6 MW
Constraint: NC-N_HUNTER1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128396PRICES SUBJECT TO REVIEW29/07/2025 10:35:25 AM

[EventId:202507291040_review] Prices for interval 29-Jul-2025 10:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128395PRICES SUBJECT TO REVIEW29/07/2025 10:30:17 AM

[EventId:202507291035_review] Prices for interval 29-Jul-2025 10:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128394PRICES SUBJECT TO REVIEW29/07/2025 10:25:34 AM

[EventId:202507291030_review] Prices for interval 29-Jul-2025 10:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1025 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128393PRICES SUBJECT TO REVIEW29/07/2025 10:20:20 AM

[EventId:202507291025_review] Prices for interval 29-Jul-2025 10:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm