STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE - VIC region - 06/08/2025
Inter-regional transfer limit variation - Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE - VIC region - 06/08/2025
A planned outage of Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE in the VIC region was scheduled from 0700 hrs 06/08/2025 to 1800 hrs 06/08/2025.
The outage has been completed and Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE returned to service at 0945 hrs 06/08/2025
Constraint set(s) revoked: V-KO_WE_RC
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South East 275 kV No. 2 SVC - SA region - 05/08/2025
Inter-regional transfer limit variation - South East 275 kV No. 2 SVC - SA region - 05/08/2025
At 2036 hrs 05/08/2025 there was an unplanned outage of South East 275 kV No. 2 SVC.
The following constraint set(s) invoked at 2045 hrs 05/08/2025
S-SE_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.
AEMO Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 02/08/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_57A00625 from 1235 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
NSW1-QLD1
Manager NEM Real Time Operations
[EventId:202507291015_confirmed] Prices for interval 29-Jul-2025 10:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 29 July 2025
PRICES ARE NOW CONFIRMED for trading interval 29-Jul-2025 10:15.
In accordance with Market Notice 128391 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507291040_confirmed] Prices for interval 29-Jul-2025 10:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 29 July 2025
PRICES ARE NOW CONFIRMED for trading interval 29-Jul-2025 10:40.
In accordance with Market Notice 128396 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202507291035_confirmed] Prices for interval 29-Jul-2025 10:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 29 July 2025
PRICES ARE NOW CONFIRMED for trading interval 29-Jul-2025 10:35.
In accordance with Market Notice 128395 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.