NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025
NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MRTLSWF1
Duration: 25/06/2025 16:05 to 25/06/2025 17:05
Amount: -67 MW
Constraint: NC-V_MRTLSWF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#4
Duration: 25/06/2025 15:35 to 25/06/2025 15:45
Amount: -50 MW
Constraint: NC-Q_TARONG#4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025
NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LVES1
Duration: 25/06/2025 14:25 to 25/06/2025 14:45
Amount: 63 MW
Constraint: NC-V_LVES1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ULPBESS1
Duration: 25/06/2025 14:25 to 25/06/2025 14:40
Amount: 6 MW
Constraint: NC-Q_ULPBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.