128458POWER SYSTEM EVENTS07/08/2025 05:40:13 AM

Non-credible contingency event - SA region - 07/08/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 07/08/2025

At 0507 hrs the Dorrien end of the Templers West to Dorrien 132 kV line and the Templers battery tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
128457RESERVE NOTICE06/08/2025 03:16:12 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.

Manager NEM Real Time Operations
     
128456RESERVE NOTICE06/08/2025 03:07:57 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.

AEMO Operations
     
128455RESERVE NOTICE06/08/2025 01:25:22 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.


Manager NEM Real Time Operations
     
128430RESERVE NOTICE04/08/2025 02:40:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.

AEMO Operations
     
128396PRICES SUBJECT TO REVIEW29/07/2025 10:35:25 AM

[EventId:202507291040_review] Prices for interval 29-Jul-2025 10:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128395PRICES SUBJECT TO REVIEW29/07/2025 10:30:17 AM

[EventId:202507291035_review] Prices for interval 29-Jul-2025 10:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128394PRICES SUBJECT TO REVIEW29/07/2025 10:25:34 AM

[EventId:202507291030_review] Prices for interval 29-Jul-2025 10:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1025 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128393PRICES SUBJECT TO REVIEW29/07/2025 10:20:20 AM

[EventId:202507291025_review] Prices for interval 29-Jul-2025 10:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 29 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jul-2025 10:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm