Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128020 is cancelled at 2000 hrs 08/07/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1720 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 924 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 4 July 2025
NON-CONFORMANCE QLD1 Region Friday, 4 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#3
Duration: 04/07/2025 16:40 to 04/07/2025 16:45
Amount: -18 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 3 July 2025
NON-CONFORMANCE NSW1 Region Thursday, 3 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/07/2025 14:05 to 03/07/2025 14:10
Amount: 13 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 3 July 2025
NON-CONFORMANCE QLD1 Region Thursday, 3 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ULPBESS1
Duration: 03/07/2025 10:50 to 03/07/2025 11:00
Amount: 7 MW
Constraint: NC-Q_ULPBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 1 July 2025
NON-CONFORMANCE QLD1 Region Tuesday, 1 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 01/07/2025 01:45 to 01/07/2025 01:55
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Taree to Pt Macquarie 964 132kV Line- NSW region - 27/06/2025
Inter-regional transfer limit variation - Taree to Pt Macquarie 964 132kV Line - NSW region - 27/06/2025
At 0800 hrs 27/06/2025 there was a short notice outage of Taree to Pt Macquarie 964 132kV Line.
The following constraint set(s) invoked at 0755 hrs 27/06/2025
N-TAPM_964
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 26 June 2025
NON-CONFORMANCE SA1 Region Thursday, 26 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ADPBA1
Duration: 26/06/2025 07:40 to 26/06/2025 10:00
Amount: -6 MW
Constraint: NC-S_ADPBA1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025
NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MRTLSWF1
Duration: 25/06/2025 16:05 to 25/06/2025 17:05
Amount: -67 MW
Constraint: NC-V_MRTLSWF1
Auto-generated on behalf of Manager NEM Real Time Operations