PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
Completed - CHG0105078 - Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region SA1 Tuesday, 5 August 2025
NON-CONFORMANCE SA1 Region Tuesday, 5 August 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 05/08/2025 16:50 to 05/08/2025 16:55
Amount: 13 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.
AEMO Operations
CHG0104554 - Production eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0105004 - Planned system maintenance to the EMMS PreProduction Environment
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.