Market Notices

128155RECLASSIFY CONTINGENCY17/07/2025 09:41:05 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 17/07/2025 21:41 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
128153RECLASSIFY CONTINGENCY17/07/2025 05:07:13 PM

Cancellation - Reclassification of a non-credible contingency event to credible event - SA region - 15/08/2023

AEMO ELECTRICITY MARKET NOTICE.

Cancellation - Reclassification of a non-credible contingency event to credible event - SA region - 15/08/2023

Refer AEMO ELECTRICITY MARKET NOTICES 109321,109323

Based on advise received from TNSP, AEMO is satisfied that this non credible event is unlikely to re-occur.
AEMO therefore cancels this reclassification as a credible contingency event.

Region: SA

Elements: Blyth West - Munno Para 275 kV Line tripping at Blyth West end only
Cancelled: 17/07/2025 1630 hrs
Constraint(s) invoked: Nil

Manager NEM Real Time Operations
     
128152RECLASSIFY CONTINGENCY17/07/2025 04:09:50 PM

Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Cancellation time: 17/07/2025 16:09

Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 128150

Auto-generated on behalf of Manager NEM Real Time Operations
     
128151INTER-REGIONAL TRANSFER17/07/2025 03:15:24 PM

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.

The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025

Constraint set(s) revoked: Q-HACL

Manager NEM Real Time Operations
     
128150RECLASSIFY CONTINGENCY17/07/2025 03:07:35 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 17/07/2025 15:07 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
128137RESERVE NOTICE16/07/2025 07:24:19 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 128136 is cancelled at 1915 hrs 16/07/2025.

Manager NEM Real Time Operations
     
128136RESERVE NOTICE16/07/2025 06:10:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/07/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1257 MW

Manager NEM Real Time Operations
     
128134INTER-REGIONAL TRANSFER16/07/2025 01:32:26 PM

Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood M1 Transformer- VIC region - 16/07/2025

A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0700 hrs 16/07/2025 to 1800 hrs 16/07/2025.

The outage has been completed and Heywood M1 Transformer returned to service at 1335 hrs 16/07/2025

Constraint set(s) revoked: V-HYTX_M12

Manager NEM Real Time Operations
     
128132RESERVE NOTICE15/07/2025 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/07/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128131 is cancelled at 1908 hrs 15/07/2025.

Manager NEM Real Time Operations
     