Cancellation - AEMO Intervention Event - SA region 08/07/2025
Cancellation - AEMO Intervention Event - SA region 08/07/2025
Refer to Market Notice 128006
The AEMO Intervention Event and all associated directions are cancelled from 0730 hrs on 09/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128012
Direction is cancelled from: 0730 hrs 09/07/2025
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128031 is cancelled at 0025 hrs 09/07/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128020 is cancelled at 2000 hrs 08/07/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1000 hrs 11/07/2025 to 1030 hrs 11/07/2025.
The forecast capacity reserve requirement is 833 MW.
The minimum capacity reserve available is 819 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1720 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 924 MW
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 09/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 08/07/2025 to 1800 hrs 08/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1392 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128007
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0730 hrs 09/07/2025.
The direction update is issued at 1445 hrs 08/07/2025.
Manager NEM Real Time Operations