Market Notices

127865NON-CONFORMANCE25/06/2025 05:05:12 PM

NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MRTLSWF1
Duration: 25/06/2025 16:05 to 25/06/2025 17:05
Amount: -67 MW
Constraint: NC-V_MRTLSWF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127857NON-CONFORMANCE25/06/2025 03:45:12 PM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#4
Duration: 25/06/2025 15:35 to 25/06/2025 15:45
Amount: -50 MW
Constraint: NC-Q_TARONG#4

Auto-generated on behalf of Manager NEM Real Time Operations
     
127852NON-CONFORMANCE25/06/2025 02:45:13 PM

NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LVES1
Duration: 25/06/2025 14:25 to 25/06/2025 14:45
Amount: 63 MW
Constraint: NC-V_LVES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127851NON-CONFORMANCE25/06/2025 02:40:13 PM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 25/06/2025 14:25 to 25/06/2025 14:40
Amount: 6 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127835MARKET SYSTEMS25/06/2025 09:48:25 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025

Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127833NON-CONFORMANCE25/06/2025 06:10:17 AM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127802PRICES SUBJECT TO REVIEW24/06/2025 03:10:17 PM

[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127799PRICES SUBJECT TO REVIEW24/06/2025 03:05:17 PM

[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127797PRICES SUBJECT TO REVIEW24/06/2025 03:00:24 PM

[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm