Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127911 is cancelled at 0813 hrs 02/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 02/07/2025 to 2000 hrs 02/07/2025.
The forecast capacity reserve requirement is 235 MW.
The minimum capacity reserve available is 233 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127905 is cancelled at 2120 hrs 01/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1800 hrs 02/07/2025 to 2130 hrs 02/07/2025.
The forecast capacity reserve requirement is 257 MW.
The minimum capacity reserve available is 107 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127901 is cancelled at 1420 hrs 01/07/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 02/07/2025 to 2100 hrs 02/07/2025.
The forecast capacity reserve requirement is 258 MW.
The minimum capacity reserve available is 169 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 1 July 2025
NON-CONFORMANCE QLD1 Region Tuesday, 1 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 01/07/2025 01:45 to 01/07/2025 01:55
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127890 is cancelled at 2235 hrs 28/06/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 30/06/2025 to 2130 hrs 30/06/2025.
The forecast capacity reserve requirement is 1084 MW.
The minimum capacity reserve available is 945 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations