Non-credible contingency event - SA region - 07/08/2025
Non-credible contingency event - SA region - 07/08/2025
At 0507 hrs the Dorrien end of the Templers West to Dorrien 132 kV line and the Templers battery tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
Completed - CHG0105078 - Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.
AEMO Operations
CHG0104554 - Production eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0105004 - Planned system maintenance to the EMMS PreProduction Environment
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Windows Server
Change Title: Planned system maintenance to the EMMS PreProduction Environment
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.