Non-credible contingency event - SA region - 07/08/2025
Non-credible contingency event - SA region - 07/08/2025
At 0507 hrs the Dorrien end of the Templers West to Dorrien 132 kV line and the Templers battery tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Completed - CHG0105078 - Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region SA1 Tuesday, 5 August 2025
NON-CONFORMANCE SA1 Region Tuesday, 5 August 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 05/08/2025 16:50 to 05/08/2025 16:55
Amount: 13 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Refer to Market Notice 128424
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 05/08/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128432
Direction is cancelled from: 1430 hrs 05/08/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128427
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 05/08/2025.
The direction update is issued at 1600 hrs 04/08/2025.
Manager NEM Real Time Operations
CHG0104554 - Production eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128425
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/08/2025.
The direction update is issued at 1435 hrs 03/08/2025.
Manager NEM Real Time Operations