STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs to 0300 hrs 19/08/2025.
The forecast capacity reserve requirement is 411 MW.
The minimum capacity reserve available is 407 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 18/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0400 hrs to 0930 hrs 18/08/2025.
The forecast capacity reserve requirement is 405 MW.
The minimum capacity reserve available is 400 MW.
2. From 1700 hrs to 2359 hrs 18/08/2025.
The forecast capacity reserve requirement is 406 MW.
The minimum capacity reserve available is 402 MW.
AEMO Operations
NON-CONFORMANCE Region QLD1 Monday, 11 August 2025
NON-CONFORMANCE QLD1 Region Monday, 11 August 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 11/08/2025 01:00 to 11/08/2025 01:30
Amount: -16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 August 2025
NON-CONFORMANCE NSW1 Region Friday, 8 August 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/08/2025 09:35 to 08/08/2025 09:45
Amount: 140 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 5 August 2025
NON-CONFORMANCE SA1 Region Tuesday, 5 August 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 05/08/2025 16:50 to 05/08/2025 16:55
Amount: 13 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.
AEMO Operations