128359POWER SYSTEM EVENTS26/07/2025 08:58:23 AM

Update - Non-credible contingency event - NSW region - 26/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 26/07/2025

Refer AEMO Electricity Market Notice 128353

At 0832 hrs the Canberra A 132kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
128353POWER SYSTEM EVENTS26/07/2025 06:00:15 AM

Non-credible contingency event - NSW region - 26/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/07/2025

At 0449 hrs the Canberra 132 kV A Bus and the Canberra to Latham A2 132 kV Line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
128215NON-CONFORMANCE21/07/2025 06:45:14 PM

NON-CONFORMANCE Region SA1 Monday, 21 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 21 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/07/2025 18:40 to 21/07/2025 18:45
Amount: 11 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128209NON-CONFORMANCE20/07/2025 03:55:18 PM

NON-CONFORMANCE Region QLD1 Sunday, 20 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 20 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 20/07/2025 15:45 to 20/07/2025 15:55
Amount: -51 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
     
128175POWER SYSTEM EVENTS19/07/2025 01:35:42 PM

Non-credible contingency event - TAS region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/07/2025

At 1240 hrs the Liapoota - Wadamana - Palmerston 220 kV line and the Cattle Hill Wind Farm - Wadamana 220 kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of a 70 MW load reduction at Nyrstar.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128168GENERAL NOTICE18/07/2025 02:05:37 PM

Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.

This outage is considered as a High Impact Outage (HIO).

During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128159NON-CONFORMANCE18/07/2025 06:30:29 AM

NON-CONFORMANCE Region QLD1 Friday, 18 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 18 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: DDPS1
Duration: 18/07/2025 06:25 to 18/07/2025 06:30
Amount: -14 MW
Constraint: NC-Q_DDPS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128133NON-CONFORMANCE16/07/2025 07:20:23 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 16/07/2025 07:10 to 16/07/2025 07:20
Amount: 7 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     