Cancellation - AEMO Intervention Event - SA region 08/01/2025
Cancellation - AEMO Intervention Event - SA region 08/01/2025
Refer to Market Notice 122980
The AEMO Intervention Event and all associated directions are cancelled from 0910 hrs on 09/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122981
Direction is cancelled from: 0910 hrs 09/01/2025
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 9 January 2025
NON-CONFORMANCE QLD1 Region Thursday, 9 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 09/01/2025 08:15 to 09/01/2025 08:30
Amount: 35 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122980
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 08/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0930 hrs 09/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 09/01/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 08/01/2025
Direction - SA region 08/01/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 08/01/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
RESERVE NOTICE MT PASA 8 January 2025
-- January 2025 - January 2026 in Victoria.
AEMO declares Low Reserve Conditions (LRC) as per clause 4.8.4 of the National Electricity Rules (NER) for:
-- January 2025 - March 2025 in Victoria when forecast demand exceeds supply under some circumstances.
Reliability risks in New South Wales are forecast to exceed the Reliability Standard during January 2025 - January 2026, but they are impacted by transmission outages and reclassifications. As these outages and reclassifications are not considered as part of a reliability incident as per clause 3.9.3C of the NER, AEMO is not declaring LRC for New South Wales at this time.
MT PASA provides early information to the market on potential reliability issues, enabling the market to respond proactively and potentially avoid the need for AEMO intervention.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 122923 published on 7 January 2025.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National
Forecasting
AEMO
Cancellation - AEMO Intervention Event - SA region 07/01/2025
Cancellation - AEMO Intervention Event - SA region 07/01/2025
Refer to Market Notice 122948
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 122957
Direction is cancelled from: 1500 hrs 08/01/2025
Manager NEM Real Time Operations
Foreseeable AEMO intervention in SA region
Foreseeable AEMO intervention in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0930 hrs 09/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 08/01/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations