Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/10/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 25/10/2021.
The forecast capacity reserve requirement is 914 MW.
The minimum capacity reserve available is 879 MW.
AEMO Operations
CHG0070639 | Production | MSATS Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution (CATS)
Change Title: MSATS Production Release
Change Start Date & Time: 27/10/2021 17:30:00 AEST
Change End Date & Time: 28/10/2021 16:00:00 AEST
Outage Start Date & Time: 27/10/2021 17:30:00 AEST
Outage End Date & Time: 27/10/2021 19:30:00 AEST
Environment: Production
Participant Impact and Requirements:
Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage.
NMI Discovery will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Cancellation of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV
Cancellation time: 20/10/2021 14:14
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 91834
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 20/10/2021 14:00 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV
Duration: 20/10/2021 13:10 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0070617 | Completed | Pre-Production | The following gateways will have their schema upgraded to r40 to support Gas Life Support project. VENCORP AEMOMIBB
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: AEMO Gas B2B Gateway
Change Title: The following gateways will have their schema upgraded to r40 to support Gas Life Support project.
VENCORP
AEMOMIBB
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0070472 | Completed | Production | WDR MVP2 Settlements Implementation
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Settlements, EMMS - Billing
Change Title: WDR MVP2 Settlements Implementation.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation of a Non-Credible Contingency Event: Lismore - Dunoon 9U6 132kV line and Lismore - Dunoon 9U7 132kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Lismore - Dunoon 9U6 132kV and Lismore - Dunoon 9U7 132kV
Cancellation time: 19/10/2021 23:14
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 91824
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Condabri Nth - Condabri Central 7400 132kV line and Condabri Nth - Condabri Central 7401 132kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Condabri Nth - Condabri Central 7400 132kV and Condabri Nth - Condabri Central 7401 132kV
Cancellation time: 19/10/2021 21:51
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 91823
Auto-generated on behalf of Manager NEM Real Time Operations