Powercor has published the Project Specification Consultation Report (PSCR) for Deer Park Terminal Station (DPTS). Publication of this PSCR represents the first step in the Regulatory Test for Transmission (RIT-T) process.
There is currently insufficient import capacity to supply the forecast maximum demand at DPTS if a forced outage of a transformer occurs and electrical demand growth in the western growth corridor area is expected to cause exceedance of station capacity by 2030.
Powercor welcomes written submissions on materials contained in this PSCR, submissions are due on 31 July 2025.
Submissions can be provided electronically to the following email address rittenquiries@powercor.com.au with the following subject field ‘Attention: Deer Park TS’