Primary Frequency Response Test Guidelines for Semi-Scheduled Plant

02/07/2025
Market National Electricity Market
StageDraft Report
ConvenorAEMO NEM
Initiated02/07/2025
Accepting submissions?Yes
Submissions close13/08/2025

Matter under consultation

In accordance with NER clause 4.4.2A, AEMO has engaged in consultation and subsequently revised the Primary Frequency Response Requirements (PFRR), most recently in June 2024, PFRR. NER Clause 4.4.2(c1) sets out the responsibilities of Scheduled and Semi-Scheduled Generators regarding the operation of their generating systems in alignment with the PFRR. Industry experience regarding the implementation of PFRR indicates that certain semi-scheduled plant have not successfully demonstrated PFRR performance as stipulated in 4.4.2(c1).  The publication of this draft report commences AEMO’s expediated consultation under NER 4.4.2A(a), on proposed Primary Frequency Response Test Guidelines for Semi-Scheduled Plant, in accordance with the process outlined in NER 8.9.3.

The consultation process

The consultation process is outlined below. Dates are indicative only and subject to change.

Consultation steps

Dates

Draft report published

2 July 2025

Procedure change request deadline

16 July 2025

Submissions due on draft report  

13 August 2025

Final report published

24 September 2025

AEMO requests feedback on this draft document to operationsstakeholders@aemo.com.au by 5pm AEDT on 13 August 2025.