Interim Guideline for Connection of Inverter Based Loads

19/11/2026
Market National Electricity Market
StageDiscussion Paper
ConvenorAEMO NEM
Initiated19/11/2026
Accepting submissions?Yes
Submissions close17/12/2026

Timeline

  • Publication of the Interim Guideline
    19 November 2026
  • Submissions close for Interim Guideline
    17 December 2026
  • Publication of the updated Interim Guideline
    Early 2027

AEMO has published the Interim Guideline for Connection of Inverter Based Loads (IBLs) and an accompanying Frequently Asked Questions (FAQ) document.

These provide greater clarity and consistency for connecting IBLs, including data centres, to the National Electricity Market and supports industry through the transition to the new and updated access standards established through the AEMC’s Improving the NEM access standards – Package 2 rule change.

What the Interim Guideline package covers

The Interim Guideline sets out AEMO’s interim approach while new and updated technical guidelines are developed, supporting a more harmonised and predictable connection process. It is intended to be pragmatic, proportionate and fit-for-purpose, recognising that technical requirements should reflect a project’s size, location and potential impact on power system security and operation.

The accompanying FAQ document provides practical clarification on topics including modelling, studies, telemetry, registration, commissioning and staged developments.

Have your say

AEMO welcomes feedback on the Interim Guideline package, including any areas where further clarification would support its application.

Stakeholders are encouraged to provide feedback by 17 December 2026 to help inform the next update, planned for early 2027. Feedback will continue to be welcomed beyond this date and can be emailed to [email protected].

Unless otherwise requested, feedback may be published on AEMO’s website in accordance with AEMO’s consultation processes.

Webinar

Join us for a webinar on Wednesday 2 December at 2:00PM (AEST) to learn more about the Interim Guideline and the consultation process. There will also be an opportunity for stakeholders to ask questions and provide feedback during the session.

Register for webinar

For questions about the Interim Guideline or this consultation, please contact [email protected].