The consultation process
The consultation process is outlined below. Dates are indicative only and subject to change.
| Process stage | Date |
|---|---|
| Publication of Procedure Change Proposal | 17 July 2026 |
| Closing date for submissions on Procedure Change Proposal | 17 August 2026 |
| Publication of Procedure Change Report | 3 September 2026 |
| Proposed commencement of amended Procedure | 3 September 2026 |
Procedure change proposal
Electricity System and Market Rules – Clause 2.10
Date of Notice: 17 July 2026
Matter under consultation
AEMO has commenced the Procedure Change Process to propose amendments to the WEM Procedure: Rule Participant Registration Processes to undertake improvements to the application processes.
On 6 February 2025 the State Electricity Objective (SEO) replaced the Wholesale Market Objectives under section 3A of the Electricity Industry Act 2004. Following an assessment, AEMO considers the Procedure is consistent with the SEO.
Procedure Change Proposal documents
Invitation to make submissions
AEMO invites written submissions on this Procedure Change Proposal, including any alternative or additional proposals may improve the Procedure or better meet the State Electricity Objective under section 3A of the Electricity Industry Act 2004.
AEMO requests that respondents identify any parts of their submission that they wish to remain confidential, explaining why. AEMO advises that it may still publish that information if it does not consider it to be confidential, but will consult with the respondent before doing so.
When making a claim for confidentiality, AEMO encourages respondents to familiarise themselves with Chapter 10 of the Electricity System and Market Rules (ESM Rules), which imposes obligations in respect to the release of documents.
Meetings
Before the closing date for submissions, any person may request a meeting with AEMO to discuss the issues and proposed changes raised in the Procedure Change Proposal, stating why they consider a meeting is necessary or desirable.
If appropriate, meetings may be held jointly with other stakeholders.
Subject to confidentiality restrictions, AEMO generally makes details of matters discussed at meetings available to other stakeholders as part of the final published Procedure Change Report (or earlier, where applicable).
Closing date and time
Submissions in response to this Procedure Change Proposal should be sent by email to [email protected], to reach AEMO by 5.00 pm (AWST) on 13 August 2026.
All submissions must be in electronic format (pdf or Microsoft Word) and should use the Procedure Change Submission form.
AEMO is not obliged to consider submissions received after the closing date and time. Any late submissions should explain the reason for delay and the detriment expected if AEMO does not consider the late submission.
Publication
All submissions will be published on AEMO's website. Confidential information will not be published, other than as specified above.