Publishing actual intermittent generators (SCADA) availability data

Background

AEMO has received feedback from multiple participants and interested parties to publish the actual plant availability data as measured via SCADA. Publishing the actual plant availability data provides market transparency into the outage rate of intermittent generators and complements the existing published plant availability data that is submitted by participants for PD/STPASA. Furthermore, publishing this data enables participants to get an indication of the input data used to produce the AWEFS/ASEFS dispatch UIGF.

In late 2020, AEMO sought feedback from participants in the Intermittent Generator Forum on the level of support in publishing actual plant availability data. Following the forum, AEMO received support of this initiative and began scoping the necessary changes to publish the data. Further below provides the timeline of the initiative and the steps required.

Design and Operation

The actual plant availability data includes publishing the following signals and their associated quality flag (where available) on a dispatch interval (DI) basis for each intermittent generator.

  • SCADA Local Limit (LOCL): For both wind and solar farms.

  • SCADA Elements Available (ELAV):

  • Total # turbines available for wind farms.

  • Total # inverters available for solar farms.

Note, some intermittent generators do not have Local Limit and/or Turbines/Inverters Available SCADA signals available hence, these will be missing from the data set.

The data is to be published privately to the EMMS Data Model on the current day, and published publicly next-day to both the EMMS Data Model and NEMWeb. For more information on the data and format, please see the INTERMITTENT_GEN_SCADA table in the current MMS Data Model.

Milestone  Timing  Status
Feedback received from participants and interested parties to publish actual plant availability data  Up to November 2020  Complete
Sought participant feedback on publishing actual availability data in the Intermittent Generator (IG) Forum  November 2020  Complete
Confirmation AEMO will progress publishing the actual plant availability data in the IG Forum  July 2021 Complete
 Further information communicated via IG Forum and Operational Forecasting (OPF) mailing list  IG Forum: December 2021
OPF mailing list: May 2023, March 2024
 Ongoing
 New table (INTERMITTENT_GEN_SCADA) published in EMMS – Technical Specification – Data Model v5.2  May 2023  Complete
 Creation of “Publishing actual intermittent generator (SCADA) availability data” webpage.  27 March 2024  Complete
 Publishing of actual plant availability data to EMMS Data Model and NEMWeb  July 2024 (planned)  Pending

Further information


Information regarding the progress of this initiative will be communicated via the Operational Forecasting mailing list in addition to this webpage being updated.

For more information or if you would like to be added to the Operational Forecasting mailing list, please contact op.forecasting@aemo.com.au.

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm