Filter by category
Filter by Date
Request for Generator Recall Information for the period 06/12/2025 for Region NSW
Refer to AEMO Electricity Market Notice no. 131390.
Please provide Generator Recall Information for the period 06/12/2025, by 12:00 hrs on 05/12/2025 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf?rev=ffdda25d8c12434391449cb96d8da0fd
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations