[EventId:202603231145_confirmed] Prices for interval 23-Mar-2026 11:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1227 hrs on 24 March 2026
PRICES ARE NOW CONFIRMED for trading interval 23-Mar-2026 11:45.
In accordance with Market Notice 135953 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $0.45 $44.02
LOWER5MIN
NSW1 $0.00 $0.03
LOWER60SEC
NSW1 $0.00 $0.07
LOWER6SEC
NSW1 $0.00 $0.05
LOWERREG
NSW1 $0.90 $0.66
RAISE1SEC
NSW1 $0.01 $0.02
RAISE5MIN
NSW1 $0.01 $0.02
RAISE60SEC
NSW1 $0.03 $0.04
RAISE6SEC
NSW1 $0.05 $0.04
RAISEREG
NSW1 $6.98 $3.73
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 11/02/2026
Cancellation of Actual (LOR1) condition in the NSW region - 11/02/2026
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.133484 is cancelled at 1930 hrs 11/02/2026.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 11/02/2026
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 11/02/2026
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 11/02/2026 1900 hrs
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1219 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 10/02/2026
Cancellation of Actual (LOR1) condition in the SA region - 10/02/2026
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.133453 is cancelled at 2140 hrs 10/02/2026.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 10/02/2026
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 10/02/2026
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1930 hrs.
The Actual LOR1 condition is forecast to exist until 2230 hrs.
The capacity reserve requirement is 625 MW
The minimum capacity reserve available is 390 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2026
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2026
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.133306 is cancelled at 1745 hrs 05/02/2026.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2026
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2026
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 05/02/2026 1730 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1225 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026
Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.133105 is cancelled at 2145 hrs 26/01/2026.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 26/01/2026 2200 hrs
The capacity reserve requirement is 654 MW
The minimum capacity reserve available is 447 MW
Manager NEM Real Time Operations