Filter by category
Filter by Date
Update - Non-credible contingency event - QLD region - 29/05/2026
Update - Non-credible contingency event - QLD region - 29/05/2026
Refer AEMO Electricity Market Notice 144162
At 2135 hrs the Woolooga to Teebar Creek 8850 275kV Line and the Teebar Ck No2 275kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 29/05/2026
Non-credible contingency event - QLD region - 29/05/2026
At 1013 hrs the Woolooga to Teebar Creek 8850 275kV Line and the Teebar Ck No2 275kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood M1 500/275kV XFMR - VIC region - 29/05/2026
Inter-regional transfer limit variation - Heywood M1 500/275kV XFMR - VIC region - 29/05/2026
A planned outage of Heywood M1 500/275kV XFMR in the VIC region was scheduled from 1100 hrs 25/05/2026 to 1800 hrs 29/05/2026.
The outage has been completed and Heywood M1 500/275kV XFMR returned to service at 0920 hrs 29/05/2026
Constraint set(s) revoked: V-HYTX_M12
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 25/05/2026
Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 25/05/2026
At 1130 hrs 25/05/2026 there was a short notice outage of Koorangie to Wemen 220 kV Line.
The following constraint set(s) invoked at 1130 hrs 25/05/2026
V-KOWE
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tailem Bend 275 kV East Bus - SA region - 24/05/2026
Inter-regional transfer limit variation - Tailem Bend 275 kV East Bus - SA region - 24/05/2026
At 1250 hrs 24/05/2026 there was a short notice outage of Tailem Bend 275 kV East Bus.
The following constraint set(s) invoked at 1250 hrs 24/05/2026
S-TB275_E_BUS
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang F2 500/330kV XFMR - VIC region - 20/05/2026
Inter-regional transfer limit variation - South Morang F2 500/330kV XFMR - VIC region - 20/05/2026
The outage has been rescheduled for 0630 hrs 18/05/2026 to 1700 hrs 22/05/2026.
Constraint set(s) invoked: V-SMTX_F_R
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-SA,VIC1-NSW1,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Non-credible contingency event -NSW region - 17 May 2026
Update - Non-credible contingency event - NSW region - 17/05/2026
Refer AEMO Electricity Market Notice 144112
At 1327 hrs the Upper Tumut Units 1, 2, 3 and 4 were made available to return to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 17/05/2026
Non-credible contingency event - NSW region - 17/05/2026
At 2317 hrs the Upper Tumut Units 1, 2, 3 and 4 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1300 hrs 17/05/2026
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations