144186CONSTRAINTS02/06/2026 02:03:25 PM

Increase in Heywood from SA to Vic test limit from 550 to 600 MW

AEMO ELECTRICITY MARKET NOTICE

AEMO will increase the Heywood test limit from SA to Vic (from the current 550 MW) to 600 MW today to conduct internetwork testing on Heywood.

The following constraint sets will be revoked once the testing criteria met:
I-SV_HEY_550_TEST

The following constraint sets will be invoked:
I-SV_HEY_600_TEST

AEMO will revert the Heywood test limit back to 550 MW once the test has completed while the test result being analysed.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Terry Liu
AEMO Operations
     
144142CONSTRAINTS25/05/2026 02:50:50 PM

Updated system normal constraints to manage Murraylink dynamic rating forecast in pre-dispatch and PASA

Refer to Market Notice 134696

AEMO has now completed the production of the Murraylink dynamic rating forecast model and the forecasting performance has been satisfactory during the test. AEMO will be enabling the pre-dispatch and PASA formulation using the Murraylink dynamic rating forecast on the following two constraint equations at 1000 hrs on Wednesday 27th May 2026.

VSML_RAT_LIM_DYN
SVML_RAT_LIM_DYN

For full details on the formulation, the updated constraint equations have now been loaded into AEMO's pre-production systems.

Terry Liu
AEMO Operations
     
144083CONSTRAINTS15/05/2026 11:20:34 AM

Updated maximum generation contingency size in Victoria from 600 MW to 750 MW

VicGrid has conducted studies and determined that the maximum generation contingency size in Victoria can be increased from 600 MW to 750 MW.

This change affects the generator limitations for prior outage conditions especially in the South-west Victoria area. The new generation limitation for outages is now 750 MW. AEMO has implemented this change in production on 13th May 2026 by updating generation constraints to increase the generation upper limits for outage conditions.

Please refer to the Network Outage Schedule for any upcoming outages in south-west Victoria here.
https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/network-data/network-outage-schedule

For further details on this change please refer to VicGrid Limits Advice or contact VicGrid.
vicgrid.com.au/transmission-planning/planning-the-energy-grid

Terry Liu
AEMO Operations
     
134696CONSTRAINTS10/03/2026 12:18:10 PM

New system normal constraints to manage Murraylink real time dynamic rating

AEMO and APA have been working on better ways to reflect Murraylink transfer capability more accurately during high ambient temperature conditions. APA has supplied AEMO with a real time dynamic rating and AEMO will apply this in new constraint equations to dispatch Murraylink.

At this stage, the constraint equations will only be active in Dispatch timeframe.

The following two constraint equations will be implemented in constraint set V-NIL and S-NIL, at 1000 hrs on Thursday 12th March 2026:

VSML_RAT_LIM_DYN
SVML_RAT_LIM_DYN

For full details on the formulation, the new constraint equations have now been loaded into AEMO's pre-production systems.

Terry Liu
AEMO Operations
133487RESERVE NOTICE11/02/2026 07:39:56 PM

Cancellation of Actual (LOR1) condition in the NSW region - 11/02/2026

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 11/02/2026

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.133484 is cancelled at 1930 hrs 11/02/2026.

Manager NEM Real Time Operations
133484RESERVE NOTICE11/02/2026 06:08:32 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 11/02/2026

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 11/02/2026

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 11/02/2026 1900 hrs

The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1219 MW

Manager NEM Real Time Operations
133455RESERVE NOTICE10/02/2026 09:47:14 PM

Cancellation of Actual (LOR1) condition in the SA region - 10/02/2026

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 10/02/2026

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.133453 is cancelled at 2140 hrs 10/02/2026.

Manager NEM Real Time Operations
133453RESERVE NOTICE10/02/2026 07:52:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 10/02/2026

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 10/02/2026

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1930 hrs.
The Actual LOR1 condition is forecast to exist until 2230 hrs.

The capacity reserve requirement is 625 MW
The minimum capacity reserve available is 390 MW

Manager NEM Real Time Operations
133311RESERVE NOTICE05/02/2026 05:48:48 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2026

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2026

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.133306 is cancelled at 1745 hrs 05/02/2026.

Manager NEM Real Time Operations