Market Notices

133188MINIMUM SYSTEM LOAD01/02/2026 01:24:13 PM

Actual Minimum System Load MSL1 condition in the SA Region on 01/02/2026

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the SA Region on 01/02/2026

Update to Market Notice 133167 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 01/02/2026.

The advisory MSL thresholds are:
- MSL1 54 MW
- MSL2 -97 MW
- MSL3 -448 MW

The demand is below the MSL1 threshold.

Demand refers to Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .

Manager NEM Real Time Operations
133167MINIMUM SYSTEM LOAD30/01/2026 03:47:20 PM

Forecast Minimum System Load MSL1 condition in the SA Region on 01/02/2026

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the SA Region on 01/02/2026

[Update to Market Notice 133159] - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 01/02/2026.

Minimum System Load (MSL) conditions are forecast when demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1: 54 MW
- MSL2: -96 MW
- MSL3: -448 MW

The demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1230 hrs 01/02/2026 to 1330 hrs 01/02/2026. Minimum demand is forecast to be 42 MW at 1330 hrs.

Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .

AEMO Operations
133159MINIMUM SYSTEM LOAD29/01/2026 11:26:28 AM

Forecast Minimum System Load MSL1 condition in the SA Region on 01/02/2026

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 01/02/2026.

Minimum System Load (MSL) conditions are forecast when demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1: 54 MW
- MSL2: -96 MW
- MSL3: -448 MW

The demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs 01/02/2026 to 1430 hrs 01/02/2026. Minimum demand is forecast to be 36 MW at 1330 hrs.

Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .

AEMO Operations
133108RESERVE NOTICE26/01/2026 09:47:00 PM

Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.133105 is cancelled at 2145 hrs 26/01/2026.

Manager NEM Real Time Operations
133105RESERVE NOTICE26/01/2026 08:42:59 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 26/01/2026 2200 hrs

The capacity reserve requirement is 654 MW
The minimum capacity reserve available is 447 MW

Manager NEM Real Time Operations
132709MINIMUM SYSTEM LOAD11/01/2026 03:28:49 PM

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the SA Region on 11/01/2026.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the SA Region on 11/01/2026.

Cancellation - Actual MSL1- SA Region at 1530 hrs 11/01/2026.

Refer to Market Notice 132706 for MSL1.

Manager NEM Real Time Operations
132707MINIMUM SYSTEM LOAD11/01/2026 11:55:42 AM

Cancellation of ForecastMinimum System Load (MSL) MSL1 event in the VIC Region on 11/01/2026.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the VIC Region on 11/01/2026.

Cancellation - ForecastMSL1- VIC Region at 1145 hrs 11/01/2026.

Refer to Market Notice 132693for MSL1.

Manager NEM Real Time Operations
132706MINIMUM SYSTEM LOAD11/01/2026 11:50:58 AM

Actual Minimum System Load MSL1 condition in the SA Region on 11/01/2026

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the SA Region on 11/01/2026

Update to Market Notice 132699 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 11/01/2026.

Minimum demand is forecast to be -33 MW at 1330 hrs, and the advisory threshold is:
- MSL1 34 MW
- MSL2 -117 MW
- MSL3 -468 MW

The demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1600 hrs.

Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .

Manager NEM Real Time Operations
132699MINIMUM SYSTEM LOAD11/01/2026 10:04:06 AM

Update to the Forecast Minimum System Load MSL1 condition in the SA Region on 11/01/2026

AEMO ELECTRICITY MARKET NOTICE
Update to the Forecast Minimum System Load MSL1 condition in the SA Region on 11/01/2026

Update to Market Notice 132668 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the SA on 11/01/2026.

Minimum System Load (MSL) conditions are forecast when demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 34 MW
- MSL2 -117 MW
- MSL3 -468 MW

The demand is forecast to be below the MSL1 threshold for the following period:
- From 1300 hrs 11/01/2026 to 1600 hrs 11/01/2026. Minimum demand is forecast to be -24 MW at 1430 hrs.

Forecast demand refers to forecast Operational Demand that excludes contribution from Significant Non-Scheduled Generation: see definitions at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/operational-demand-data .

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm