Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 10/01/2026
In order to maintain the power system in a secure operating state in the VIC region, AEMO had invoked automated constraint set CA_BRIS_5873DCEF from 0500 hrs to 1135 hrs 11/01/2026.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1,V-SA,VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Correction - Inter-regional transfer limit variation - Multiple outage, 8848 and 8849 (Greenbank to Middle Ridge) 275kV line O/S - QLD region - 11/01/2026
Correction to Market Notice 132701
Inter-regional transfer limit variation - 8848 and 8849 (Greenbank to Middle Ridge) 275kV line O/S - QLD region - 11/01/2026
At 1130 hrs 11/01/2026 there will be a short notice outage of 8848 and 8849 (Greenbank to Middle Ridge) 275kV lines.
The following constraint set(s) invoked at 11:30 hrs 11/01/2026
Q-MRGB_8848_8849
Q-X_MRGB_MRGB
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Multiple outage, 8848 and 8849 (Greenbank to Middle Ridge) 275kV line O/S - QLD region - 11/01/2026
Inter-regional transfer limit variation - 8848 and 8849 (Greenbank to Middle Ridge) 275kV line O/S - QLD region - 11/01/2026
At 1130 hrs 11/01/2026 there will be a short notice outage of 8848 and 8849 (Greenbank to Middle Ridge) 275kV lines.
The following constraint set(s) invoked at 0800 hrs 13/01/2026
Q-MRGB_8848_8849
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Woolooga 275kV SVC - QLD region - 11/01/2026
Inter-regional transfer limit variation - Woolooga 275kV SVC - QLD region - 11/01/2026
At 0138 hrs 11/01/2026 there was an unplanned outage of Woolooga 275kV SVC.
The following constraint set(s) invoked at 0145 hrs 11/01/2026
Q-WO_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Kerang SVC - VIC region - 10/01/2026
Inter-regional transfer limit variation - Kerang SVC - VIC region - 10/01/2026
At 0825 hrs 10/01/2026 there was an unplanned outage of Kerang SVC .
The following constraint set(s) invoked at 0830 hrs 10/01/2026
V-KGTS_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 10/01/2026
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_5873DCEF from 0500 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
VIC-SA
Manager NEM Real Time Operations
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 09/01/2026
Cancellation- Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 09/01/2026
Refer market notice: 132616
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_58730C07 from 1410 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dederang - South Morang No2 330kV line - VIC region - 09/01/2026
Inter-regional transfer limit variation - Dederang - South Morang No2 330kV line - VIC region - 09/01/2026
At 1700 hrs 09/01/2026 there was an unplanned outage of Dederang - South Morang No2 330kV line.
The following constraint set(s) invoked at 1720 hrs 09/01/2026
V-DBUSS_T
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dederang - Murray No 67 330kV line - VIC region - 09/01/2026
Inter-regional transfer limit variation - Dederang - Murray No 67 330kV line - VIC region - 09/01/2026
At 1603 hrs 09/01/2026 there was an unplanned outage of Dederang - Murray No 67 330kV line.
The following constraint set(s) invoked at 1610 hrs 09/01/2026
V-DDMS
V-DBUSS_L
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,NSW1-QLD1,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations