Inter-regional transfer limit variation - Greenbank 275 kV SVC - QLD region - 02/03/2026
Inter-regional transfer limit variation - Greenbank 275 kV SVC - QLD region - 02/03/2026
At 1200 hrs 02/03/2026 there was a short notice outage of Greenbank 275 kV SVC.
The following constraint set(s) invoked at 1200 hrs 02/03/2026
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Black Range No.2 275 kV Series Capacitor - SA region - 27/02/2026
Inter-regional transfer limit variation - Black Range No.2 275 kV Series Capacitor - SA region - 27/02/2026
At 1840 hrs 27/02/2026 there was an unplanned outage of of Black Range No.2 275 kV Series Capacitor.
The following constraint set invoked at 1850 hrs 27/02/2026
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlk_Q Terranora 9901 110kV LINE - NSW region - 12/02/2026
Inter-regional transfer limit variation - Directlk_Q Terranora 9901 110kV LINE - NSW region - 12/02/2026
At 1030 hrs 12/02/2026 there was a short notice outage of Directlk_Q Terranora 9901 110kV LINE.
The following constraint set(s) invoked at 1230 hrs 12/02/2026
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Mudgeeraba No 5 275/110kV transformer - QLD region - 09/02/2026
Inter-regional transfer limit variation -Mudgeeraba No 5 275/110kV transformer - QLD region - 09/02/2026
At 0801 hrs 09/02/2026 there was an unplanned outage of Mudgeeraba No 5 275/110kV transformer.
The following constraint set(s) invoked at 0805 hrs 09/02/2026
Q-MUTX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood No 110 275kV circuit breaker - VIC region - 08/02/2026
Inter-regional transfer limit variation - Heywood No 110 275kV circuit breaker - VIC region - 08/02/2026
At 1530 hrs 08/02/2026 there was a short notice outage of Heywood No 110 275kV circuit breaker.
The following constraint set(s) invoked at 1530 hrs 08/02/2026
V-HYTX_M12
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Balranald - Buronga X3 220 kV line - NSW region - 03/02/2026
Inter-regional transfer limit variation - Balranald - Buronga X3 220 kV line- NSW region - 03/02/2026
A planned outage of Balranald - Buronga X3 220 kV line in the NSW region was scheduled from 2130 hrs 19/01/2026 to 0900 hrs 04/02/2026.
The outage has been completed and Balranald - Buronga X3 220 kV line returned to service at 1945 hrs 03/02/2026
Constraint set revoked: N-BABU
This constraint set contains equations with the following interconnectors on the LHS.
VIC1-NSW1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - QLD region - 28/01/2026
Inter-regional transfer limit variation - Middle Ridge - Greenbank 8848 & 8849 275 kV lines- QLD region - 28/01/2026
At 1614 hrs 28/01/2026 there was a short notice outage of Middle Ridge - Greenbank 8848 & 8849 275 kV lines.
The following constraint sets invoked at 1600 hrs 28/01/2026
Q-MRGB_8848_8849
Q-X_MRGB_MRGB
This constraint sets contain equations with the following interconnectors on the LHS.
NSW1QLD1
N-Q_MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 27/01/2026
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_588AFB91 from 1755 hrs to 2110 hrs.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 27/01/2026
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_588AF9C5 from 1745 hrs to 1755 hrs.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
Manager NEM Real Time Operations