Inter-regional transfer limit variation - Dumaresq-Sapphire (8J) 330 kV Line - NSW region - 01/05/2026
Inter-regional transfer limit variation - Dumaresq-Sapphire (8J) 330 kV Line - NSW region - 01/05/2026
A planned outage of Dumaresq-Sapphire (8J) 330 kV Line in the NSW region was scheduled from 1430 hrs 01/05/2026 to 1530 hrs 01/05/2026.
The outage has been rescheduled for 0940 hrs 01/05/2026 to 1040 hrs 01/05/2026.
The following constraint set(s) invoked at 0940 hrs 01/05/2026
N-DMSR_8J
N-X_8J+DM+TW_SVC
N-SAPHWF1_ZERO
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - QNI Interconnector - NSW region - 29/04/2026
Inter-regional transfer limit variation - QNI Interconnector - NSW region - 29/04/2026
At 1740 hrs 29/04/2026 based on advise received from the TNSP, the QNI Interconnector has been further restricted during the outage of Armidale - Sapphire 8E 330kV Line.
The outage is scheduled for 0700 hrs 26/04/2026 to 1700 hrs 02/05/2026.
The following constraint set(s) invoked at 1740 hrs 29/04/2026
I-QN_550
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No.1 275kV SVC - SA region - 26/04/2026
Inter-regional transfer limit variation - Para No.1 275kV SVC - SA region - 26/04/2026
An outage of Para No.1 275kV SVC in the SA region was scheduled from 1024 hrs 20/04/2026 to 1700 hrs 28/04/2026.
The outage has been completed and Para No.1 275kV SVC returned to service at 1955 hrs 26/04/2026
Constraint set(s) revoked: S-PA_VC1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Newcastle - Eraring500 93 330kV Line - NSW region - 25/04/2026
Inter-regional transfer limit variation - Newcastle - Eraring500 93 330kV Line - NSW region - 25/04/2026
A planned outage of Newcastle - Eraring500 93 330kV Line in the NSW region was scheduled from 0700 hrs 07/04/2026 to 1700 hrs 27/04/2026.
The outage has been completed and Newcastle - Eraring500 93 330kV Line returned to service at 1350 hrs 25/04/2026
Constraint set(s) revoked: N-ERNC_93
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 20/04/2026
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 20/04/2026
At 1024 hrs there was an unplanned outage of Para No 1 SVC.
Constraint set(s) invoked: S-PA_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS:
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Tarrone to Heywood/APD 500 kV Line - VIC region - 17/04/2026
Inter-regional transfer limit variation - Tarrone to Heywood/APD 500 kV Line - VIC region - 17/04/2026
At 1152 hrs 17/04/2026 there was an unplanned outage of Tarrone to Heywood/APD 500 kV Line.
The following constraint set(s) invoked at 1200 hrs 17/04/2026
V-HYTR
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,T-V-MNSP1,VIC1-NSW1,NSW1-QLD1,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 17/04/2026
Cancellation - AEMO Intervention Event - SA region 06/04/2026
Refer to Market Notice 141104
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 17/04/2026.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Origin Energy Electricity Limited - QUARANTINE PS UNIT 5
Cancellation: Direction issued to: Origin Energy Electricity Limited - QUARANTINE PS UNIT 5
Refer to Market Notice 141105, 141110, 141111
Direction is cancelled from: 1600 hrs 17/04/2026
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Bayswater-Wollar 5A4 500kV LINE- NSW region - 17/04/2026
Inter-regional transfer limit variation - Bayswater-Wollar 5A4 500kV LINE - NSW region - 17/04/2026
A planned outage of Bayswater-Wollar 5A4 500kV LINE in the NSW region was scheduled from 0700 hrs 08/04/2026 to 1700 hrs 17/04/2026.
The outage has been completed and Bayswater-Wollar 5A4 500kV LINE returned to service at 1010 hrs 17/04/2026
Constraint set(s) revoked: N-BWWO_5A4