NON-CONFORMANCE Region QLD1 Saturday, 11 April 2026
NON-CONFORMANCE QLD1 Region Saturday, 11 April 2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/04/2026 12:05 to 11/04/2026 12:15
Amount: -15 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 10/04/2026
Non-credible contingency event - TAS region - 10/04/2026
At 1646 hrs the Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, the Farrell - Reece No.1 and No.2 220 kV lines are considered vulnerable with a category of probable due to lightning.
At the time of the trip, Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV lines were not reclassified due to lightning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event from 16:50 hrs until further notice.
Refer market notice 141010
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - refer market notice 140994
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: RYANCWF1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 139 MW
Constraint: NC-V_RYANCWF1
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - Refer market notice 140993
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST2
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 237 MW
Constraint: NC-V_GPWFEST2
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - refer to market notice 104992
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 239 MW
Constraint: NC-V_GPWFEST1
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - Refer to market notice 140990
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ELAINWF1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 74 MW
Constraint: NC-V_ELAINWF1
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: RYANCWF1
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 139 MW
Constraint: NC-V_RYANCWF1
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST2
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 237 MW
Constraint: NC-V_GPWFEST2
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST1
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 239 MW
Constraint: NC-V_GPWFEST1
Manager NEM Real Time Operations