Market Notices

136764RESERVE NOTICE25/03/2026 05:35:17 AM

PDPASA - Suspect Lack Of Reserve Level 1 (LOR1) in the Qld Region on 25/03/2026

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there is a suspect Forecast LOR1 condition for the Qld region for the following period:

[1.] From 2030 hrs to 2100 hrs on 25/03/2026.

AEMO is currently investigating this LOR1 forecast condition to confirm whether it is valid.

Manager NEM Real Time Operations
136454PRICE ADJUSTMENT24/03/2026 12:27:46 PM

[EventId:202603231145_confirmed] Prices for interval 23-Mar-2026 11:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1227 hrs on 24 March 2026

PRICES ARE NOW CONFIRMED for trading interval 23-Mar-2026 11:45.

In accordance with Market Notice 135953 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $0.45 $44.02
LOWER5MIN
NSW1 $0.00 $0.03
LOWER60SEC
NSW1 $0.00 $0.07
LOWER6SEC
NSW1 $0.00 $0.05
LOWERREG
NSW1 $0.90 $0.66
RAISE1SEC
NSW1 $0.01 $0.02
RAISE5MIN
NSW1 $0.01 $0.02
RAISE60SEC
NSW1 $0.03 $0.04
RAISE6SEC
NSW1 $0.05 $0.04
RAISEREG
NSW1 $6.98 $3.73


This is an AEMO autogenerated Market Notice.
134785SETTLEMENTS RESIDUE13/03/2026 05:00:33 PM

[EventId:202603131700_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 March 2026 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 13 March 2026

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 March 2026.

Refer to market notice: 134782

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1700 hrs on 13 March 2026.

This is an AEMO autogenerated Market Notice.
134782SETTLEMENTS RESIDUE13/03/2026 04:05:23 PM

[EventId:202603131605_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 13 March 2026 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 13 March 2026

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 March 2026.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1605 hrs on 13 March 2026.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
134779SETTLEMENTS RESIDUE13/03/2026 01:45:30 PM

[EventId:202603131345_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 March 2026 13:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1345 hrs on 13 March 2026

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 March 2026.

Refer to market notice: 134777

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1345 hrs on 13 March 2026.

This is an AEMO autogenerated Market Notice.
134778SETTLEMENTS RESIDUE13/03/2026 01:30:50 PM

[EventId:202603131330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 March 2026 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 March 2026

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2026.

Refer to market notice: 134774

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 13 March 2026.

This is an AEMO autogenerated Market Notice.
134777SETTLEMENTS RESIDUE13/03/2026 01:15:33 PM

[EventId:202603131315_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 13 March 2026 13:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 13 March 2026

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 March 2026.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1315 hrs on 13 March 2026.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
134776SETTLEMENTS RESIDUE13/03/2026 01:00:38 PM

[EventId:202603131300_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 March 2026 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 13 March 2026

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 March 2026.

Refer to market notice: 134771

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1300 hrs on 13 March 2026.

This is an AEMO autogenerated Market Notice.
134774SETTLEMENTS RESIDUE13/03/2026 12:35:38 PM

[EventId:202603131235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 March 2026 12:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1235 hrs on 13 March 2026

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2026.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 13 March 2026.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.