133306RESERVE NOTICE05/02/2026 04:07:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2026

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2026

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 05/02/2026 1730 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1225 MW

Manager NEM Real Time Operations
133108RESERVE NOTICE26/01/2026 09:47:00 PM

Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 26/01/2026

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.133105 is cancelled at 2145 hrs 26/01/2026.

Manager NEM Real Time Operations
133105RESERVE NOTICE26/01/2026 08:42:59 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 26/01/2026

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 26/01/2026 2200 hrs

The capacity reserve requirement is 654 MW
The minimum capacity reserve available is 447 MW

Manager NEM Real Time Operations
133103RESERVE NOTICE26/01/2026 08:13:38 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 2100 hrs 26/01/2026 to 2130 hrs 26/01/2026.
The forecast capacity reserve requirement is 651 MW.
The minimum capacity reserve available is 538 MW.


Manager NEM Real Time Operations
133095RESERVE NOTICE26/01/2026 03:41:56 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 133093 is cancelled at 1545 hrs 26/01/2026.

Manager NEM Real Time Operations
133093RESERVE NOTICE26/01/2026 02:16:09 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 133091 has been updated at 1408 hrs to the following:


[1.] From 2030 hrs 26/01/2026 to 2100 hrs 26/01/2026.
The forecast capacity reserve requirement is 645 MW.
The minimum capacity reserve available is 592 MW.


Manager NEM Real Time Operations
133091RESERVE NOTICE26/01/2026 12:27:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 133090 has been updated at 1212 hrs to the following:


[1.] From 1830 hrs 26/01/2026 to 2130 hrs 26/01/2026.
The forecast capacity reserve requirement is 640 MW.
The minimum capacity reserve available is 496 MW.


Manager NEM Real Time Operations
133090RESERVE NOTICE26/01/2026 10:43:13 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 133088 has been updated at 1038 hrs to the following:


[1.] From 1830 hrs 26/01/2026 to 2130 hrs 26/01/2026.
The forecast capacity reserve requirement is 652 MW.
The minimum capacity reserve available is 646 MW.


Manager NEM Real Time Operations
133088RESERVE NOTICE26/01/2026 08:22:54 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 26/01/2026

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 133074 has been updated to the following:


From 1830 hrs 26/01/2026 to 2130 hrs 26/01/2026.
The forecast capacity reserve requirement is 655 MW.
The minimum capacity reserve available is 419 MW.