NON-CONFORMANCE Region QLD1 Saturday, 11 April 2026
NON-CONFORMANCE QLD1 Region Saturday, 11 April 2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/04/2026 12:05 to 11/04/2026 12:15
Amount: -15 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - refer market notice 140994
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: RYANCWF1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 139 MW
Constraint: NC-V_RYANCWF1
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - Refer market notice 140993
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST2
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 237 MW
Constraint: NC-V_GPWFEST2
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - refer to market notice 104992
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 239 MW
Constraint: NC-V_GPWFEST1
Manager NEM Real Time Operations
Update - NON-CONFORMANCE VIC Region - 10/04/2026
Update - Refer to market notice 140990
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ELAINWF1
Duration: 1035 HRS 10/04/2026 to 1040 HRS 10/04/2026
Amount: 74 MW
Constraint: NC-V_ELAINWF1
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: RYANCWF1
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 139 MW
Constraint: NC-V_RYANCWF1
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST2
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 237 MW
Constraint: NC-V_GPWFEST2
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GPWFEST1
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 239 MW
Constraint: NC-V_GPWFEST1
Manager NEM Real Time Operations
NON-CONFORMANCE VIC Region - 10/04/2026
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ELAINWF1
Duration: 1035 HRS 10/04/2026 to 1035 HRS 10/04/2026
Amount: 74 MW
Constraint: NC-V_ELAINWF1
Manager NEM Real Time Operations