Market Notices

143505INTER-REGIONAL TRANSFER25/04/2026 02:17:14 PM

Inter-regional transfer limit variation - Newcastle - Eraring500 93 330kV Line - NSW region - 25/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Newcastle - Eraring500 93 330kV Line - NSW region - 25/04/2026

A planned outage of Newcastle - Eraring500 93 330kV Line in the NSW region was scheduled from 0700 hrs 07/04/2026 to 1700 hrs 27/04/2026.

The outage has been completed and Newcastle - Eraring500 93 330kV Line returned to service at 1350 hrs 25/04/2026

Constraint set(s) revoked: N-ERNC_93

Manager NEM Real Time Operations
     
141819INTER-REGIONAL TRANSFER20/04/2026 10:41:01 AM

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 20/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 20/04/2026

At 1024 hrs there was an unplanned outage of Para No 1 SVC.

Constraint set(s) invoked: S-PA_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS:
V-SA,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
141109INTER-REGIONAL TRANSFER17/04/2026 12:21:23 PM

Inter-regional transfer limit variation -Tarrone to Heywood/APD 500 kV Line - VIC region - 17/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tarrone to Heywood/APD 500 kV Line - VIC region - 17/04/2026

At 1152 hrs 17/04/2026 there was an unplanned outage of Tarrone to Heywood/APD 500 kV Line.

The following constraint set(s) invoked at 1200 hrs 17/04/2026
V-HYTR

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,T-V-MNSP1,VIC1-NSW1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
141106INTER-REGIONAL TRANSFER17/04/2026 10:07:53 AM

Inter-regional transfer limit variation - Bayswater-Wollar 5A4 500kV LINE- NSW region - 17/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bayswater-Wollar 5A4 500kV LINE - NSW region - 17/04/2026

A planned outage of Bayswater-Wollar 5A4 500kV LINE in the NSW region was scheduled from 0700 hrs 08/04/2026 to 1700 hrs 17/04/2026.

The outage has been completed and Bayswater-Wollar 5A4 500kV LINE returned to service at 1010 hrs 17/04/2026

Constraint set(s) revoked: N-BWWO_5A4

Manager NEM Real Time Operations
     
141090INTER-REGIONAL TRANSFER16/04/2026 02:48:29 PM

Inter-regional transfer limit variation - Avon -Marulan 16 330kV LINE - NSW region - 16/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Avon -Marulan 16 330kV LINE - NSW region - 16/04/2026

A planned outage of Avon -Marulan 16 330kV LINE in the NSW region was scheduled from 0700 hrs 16/04/2026 to 1700 hrs 16/04/2026.

The outage has been completed and Avon -Marulan 16 330kV LINE returned to service at 1450 hrs 16/04/2026

Constraint set(s) revoked: N-AVMN_16

Manager NEM Real Time Operations
     
140921INTER-REGIONAL TRANSFER05/04/2026 02:44:02 AM

Inter-regional transfer limit variation - Larcom Creek - Calliope River 8859 275kV line - QLD region - 05/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Larcom Creek - Calliope River 8859 275kV line - QLD region - 05/04/2026

At 0232 hrs 05/04/2026 there was an unplanned outage of Larcom Creek - Calliope River 8859 275kV line.

The following constraint set(s) invoked at 0240 hrs 05/04/2026
Q-LCCP_8859

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
140906INTER-REGIONAL TRANSFER04/04/2026 01:14:16 PM

Inter-regional transfer limit variation - Armidale- Dumarsq330 8C 330 kV line - NSW region - 04/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale- Dumarsq330 8C 330 kV line - NSW region - 04/04/2026

A planned outage of Armidale- Dumarsq330 8C 330 kV line in the NSW region was scheduled from 0700 hrs 21/03/2026 to 1600 hrs 04/04/2026.

The outage has been completed and Armidale- Dumarsq330 8C 330 kV line returned to service at 1315 hrs 04/04/2026

Constraint set(s) revoked: N-X_8C+DM+TW_SVC

Manager NEM Real Time Operations
     
140733INTER-REGIONAL TRANSFER04/04/2026 05:31:21 AM

Inter-regional transfer limit variation - Para No 2 SVC - SA region - 04/04/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para No 2 SVC - SA region - 04/04/2026

At 0457 hrs there was an unplanned outage of Para No 2 SVC.

Constraint set(s) invoked: S-PA_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
137356INTER-REGIONAL TRANSFER26/03/2026 03:36:40 PM

Inter-regional transfer limit variation -Alc/prtlnd A2 500/220/33kV XFMR- VIC region - 26/03/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Alc/Prtlnd A2 500/220/33kV XFMR - VIC region - 26/03/2026

At 1515 hrs 26/03/2026 there was a short notice outage of Alc/Prtlnd A2 500/220/33kV XFMR

The following constraint set(s) invoked at 1530 hrs 26/03/2026
F-I_ML_APD_LOAD

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations