Market Notices

143187RECLASSIFY CONTINGENCY23/04/2026 06:54:01 PM

Reclassification of a Non-Credible Contingency Event: Mudgeeraba - Terranora No.757 110 kV line and Mudgeeraba - Terranora No.758 110 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Mudgeeraba - Terranora No.757 110 kV and Mudgeeraba - Terranora No.758 110 kV

Duration: 23/04/2026 18:53 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
141103RECLASSIFY CONTINGENCY17/04/2026 12:54:10 AM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 17/04/2026 00:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 141102

Auto-generated on behalf of Manager NEM Real Time Operations
     
141102RECLASSIFY CONTINGENCY16/04/2026 11:53:15 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 16/04/2026 23:53 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
141101RECLASSIFY CONTINGENCY16/04/2026 11:04:11 PM

Cancellation of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Cancellation time: 16/04/2026 23:04

Constraint set(s) revoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 141098

Auto-generated on behalf of Manager NEM Real Time Operations
     
141100RECLASSIFY CONTINGENCY16/04/2026 10:09:11 PM

Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Cancellation time: 16/04/2026 22:09

Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 141097

Auto-generated on behalf of Manager NEM Real Time Operations
     
141099RECLASSIFY CONTINGENCY16/04/2026 10:04:10 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 16/04/2026 22:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 141092

Auto-generated on behalf of Manager NEM Real Time Operations
     
141098RECLASSIFY CONTINGENCY16/04/2026 10:03:41 PM

Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Duration: 16/04/2026 22:03 until further notice

Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
141097RECLASSIFY CONTINGENCY16/04/2026 09:05:59 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 16/04/2026 21:05 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
141095RECLASSIFY CONTINGENCY16/04/2026 08:49:10 PM

Cancellation of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV

Cancellation time: 16/04/2026 20:49

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 141094

Auto-generated on behalf of Manager NEM Real Time Operations
     