Market Notices

144205RESERVE NOTICE07/06/2026 10:50:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 0800 hrs 10/06/2026 to 1000 hrs 10/06/2026.
The forecast capacity reserve requirement is 744 MW.
The minimum capacity reserve available is 542 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
144204INTER-REGIONAL TRANSFER05/06/2026 07:28:17 PM

Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 05/06/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 05/06/2026

A planned outage of Koorangie to Wemen 220 kV Line in the VIC region was scheduled from 1130 hrs 25/05/2026 to 1700 hrs 08/06/2026.

The outage has been completed and Koorangie to Wemen 220 kV Line returned to service at 1920 hrs 05/06/2026

Constraint set(s) revoked: V-KOWE

Manager NEM Real Time Operations
     
144203NON-CONFORMANCE05/06/2026 01:40:11 PM

NON-CONFORMANCE Region QLD1 Friday, 5 June 2026

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 5 June 2026

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WOOLGSF1
Duration: 05/06/2026 12:15 to 05/06/2026 13:40
Amount: 7 MW
Constraint: NC-Q_WOOLGSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
144202NON-CONFORMANCE05/06/2026 12:00:10 PM

NON-CONFORMANCE Region QLD1 Friday, 5 June 2026

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 5 June 2026

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WOOLGSF1
Duration: 05/06/2026 11:35 to 05/06/2026 12:00
Amount: 69 MW
Constraint: NC-Q_WOOLGSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
144201INTER-REGIONAL TRANSFER05/06/2026 11:45:37 AM

Inter-regional transfer limit variation - Directlink - NSW region

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink No. 3 Leg - NSW region - 05/06/2026

A planned outage of Directlink No. 3 Leg in the NSW region was scheduled from 0700 hrs 01/06/2026 to 1600 hrs 08/06/2026.

The outage has been completed and Directlink No. 3 Leg returned to service at 1150 hrs 05/05/2026

Constraint set(s) revoked: N-MBTE_1

Manager NEM Real Time Operations
     
144188NON-CONFORMANCE02/06/2026 03:40:17 PM

NON-CONFORMANCE Region QLD1 Tuesday, 2 June 2026

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 2 June 2026

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 02/06/2026 15:30 to 02/06/2026 15:40
Amount: -26 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
144165NON-CONFORMANCE29/05/2026 04:10:08 PM

NON-CONFORMANCE Region QLD1 Friday, 29 May 2026

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 29 May 2026

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 29/05/2026 16:05 to 29/05/2026 16:10
Amount: -23 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
144161NON-CONFORMANCE29/05/2026 10:45:18 AM

NON-CONFORMANCE Region NSW1 Friday, 29 May 2026

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 29 May 2026

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NESBESS1
Duration: 29/05/2026 10:40 to 29/05/2026 10:45
Amount: -101 MW
Constraint: NC-N_NESBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
144160INTER-REGIONAL TRANSFER29/05/2026 09:48:13 AM

Inter-regional transfer limit variation - Heywood M1 500/275kV XFMR - VIC region - 29/05/2026

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood M1 500/275kV XFMR - VIC region - 29/05/2026

A planned outage of Heywood M1 500/275kV XFMR in the VIC region was scheduled from 1100 hrs 25/05/2026 to 1800 hrs 29/05/2026.

The outage has been completed and Heywood M1 500/275kV XFMR returned to service at 0920 hrs 29/05/2026

Constraint set(s) revoked: V-HYTX_M12

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm