STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 144213 is cancelled at 0220 hrs 09/06/2026.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 144212 has been updated to the following:
[1.] From 1030 hrs 10/06/2026 to 1230 hrs 10/06/2026.
The forecast capacity reserve requirement is 530 MW.
The minimum capacity reserve available is 517 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which permission can be withheld for an upcoming planned outage is 0800 hrs on 10/06/2026.
Manager NEM Real Time Operations
STPASA - Update to Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
Refer to MN 144207
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1030 hrs 10/06/2026 to 1100 hrs 10/06/2026.
The forecast capacity reserve requirement is 570 MW.
The minimum capacity reserve available is 566 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which permission can be withheld for an upcoming planned outage is 0800 hrs on 09/06/2026.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 144205 has been updated to the following:
[1.] From 0800 hrs 10/06/2026 to 1100 hrs 10/06/2026.
The forecast capacity reserve requirement is 606 MW.
The minimum capacity reserve available is 443 MW.
[2.] From 1530 hrs 10/06/2026 to 1630 hrs 10/06/2026.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 379 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 144205 has been updated to the following:
[1.] From 0830 hrs 10/06/2026 to 1700 hrs 10/06/2026.
The forecast capacity reserve requirement is 571 MW.
The minimum capacity reserve available is 384 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/06/2026
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 0800 hrs 10/06/2026 to 1000 hrs 10/06/2026.
The forecast capacity reserve requirement is 744 MW.
The minimum capacity reserve available is 542 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 05/06/2026
Inter-regional transfer limit variation - Koorangie to Wemen 220 kV Line - VIC region - 05/06/2026
A planned outage of Koorangie to Wemen 220 kV Line in the VIC region was scheduled from 1130 hrs 25/05/2026 to 1700 hrs 08/06/2026.
The outage has been completed and Koorangie to Wemen 220 kV Line returned to service at 1920 hrs 05/06/2026
Constraint set(s) revoked: V-KOWE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region
Inter-regional transfer limit variation - Directlink No. 3 Leg - NSW region - 05/06/2026
A planned outage of Directlink No. 3 Leg in the NSW region was scheduled from 0700 hrs 01/06/2026 to 1600 hrs 08/06/2026.
The outage has been completed and Directlink No. 3 Leg returned to service at 1150 hrs 05/05/2026
Constraint set(s) revoked: N-MBTE_1
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 29/05/2026
Update - Non-credible contingency event - QLD region - 29/05/2026
Refer AEMO Electricity Market Notice 144162
At 2135 hrs the Woolooga to Teebar Creek 8850 275kV Line and the Teebar Ck No2 275kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations