Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53411
There is no longer any lightning activity has ceased in the vicinity of the the Farrell - Reece No. 1 and No. 2 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1040 hrs.
Constraint Sets F-T-FARE_N-2 revoked.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chapel Street - Liapootah No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Chapel Street - Liapootah No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Lightning is occurring near the Chapel Street - Liapootah No. 1 and No. 2 220 kV Lines.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1040 hrs 19 May 2016 until further notice.
Constraint Set T-CSLI_N-2 invoked
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Sheffield No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - Sheffield No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Lightning is occurring near the Farrell - Sheffield No. 1 and No. 2 220 kV Lines.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1015 hrs 19 May 2016 until further notice.
Constraint Sets: F-T-FASH_N-2 T-FASH_N-2_HM_C invoked
These Constraint Sets contain equations with the following interconnector on the LHS.
T-V-MNSP1
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Lightning is occurring near the Farrell- Reece No. 1 and No. 2 220 kV Lines.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1015 hrs 19 May 2016 until further notice.
Constraint Set F-T-FARE_N-2 invoked.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Lightning is occurring near the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1010 hrs 19 MAY 2016 until further notice.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Burnie - Sheffield No.2 110 kV and Sheffield - Paloona - Ulverstone 110 kV Lines in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Burnie - Sheffield No.2 110 kV and Sheffield - Paloona - Ulverstone 110 kV Lines in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53332
There is no longer any lightning activity in the vicinity of the Burnie - Sheffield No.2 110 kV and Sheffield - Paloona - Ulverstone 110 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0535hrs.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale - Derby 110 kV Line and Norwood - Scottsdale 110 kV Line in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale - Derby 110 kV Line and Norwood - Scottsdale 110 kV Line in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53334
There is no longer any lightning activity in the vicinity of the Norwood - Scottsdale - Derby 110 kV Line and Norwood - Scottsdale 110 kV Line.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0535 hrs.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53337
There is no longer any lightning activity has ceased in the vicinity of the the Farrell - Reece No. 1 and No. 2 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0535hrs.
Constraint Sets F-T-FARE_N-2 revoked.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Refer AEMO Electricity Market Notice 53335
There is no longer any lightning activity in the vicinity of the Rowville - Yallourn No.5 & No.6 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0300 hrs.
Constraint Set
V-ROYP56_R_N-2 revoked.
Manager NEM Real Time Operations