116162POWER SYSTEM EVENTS17/04/2024 06:10:18 AM

Update - Non-credible contingency event - VIC region - 17/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 17/04/2024

Refer AEMO Electricity Market Notice 116160

At 0610 hrs the Heywood No 2 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
116160POWER SYSTEM EVENTS17/04/2024 04:29:44 AM

Non-credible contingency event - VIC region - 17/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 17/04/2024

At 0414 hrs the Heywood No 2 500 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
116113PRICES SUBJECT TO REVIEW14/04/2024 09:05:18 AM

[EventId:202404140910_review] Prices for interval 14-Apr-2024 09:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0905 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 09:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116112PRICES SUBJECT TO REVIEW14/04/2024 09:00:24 AM

[EventId:202404140905_review] Prices for interval 14-Apr-2024 09:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 09:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116111PRICES SUBJECT TO REVIEW14/04/2024 08:55:17 AM

[EventId:202404140900_review] Prices for interval 14-Apr-2024 09:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0855 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 09:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116110PRICES SUBJECT TO REVIEW14/04/2024 08:50:19 AM

[EventId:202404140855_review] Prices for interval 14-Apr-2024 08:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0850 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 08:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116109PRICES SUBJECT TO REVIEW14/04/2024 08:45:24 AM

[EventId:202404140850_review] Prices for interval 14-Apr-2024 08:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 08:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116108PRICES SUBJECT TO REVIEW14/04/2024 08:40:19 AM

[EventId:202404140845_review] Prices for interval 14-Apr-2024 08:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0840 hrs on 14 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Apr-2024 08:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116098POWER SYSTEM EVENTS12/04/2024 01:39:23 PM

Update - Non-credible contingency event - TAS region - 12/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/04/2024

Refer AEMO Electricity Market Notice 116095

At 1304 hrs the Sheffield - Farrell No.2 220 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     