Market Notices

116299POWER SYSTEM EVENTS24/04/2024 10:54:59 AM

Non-credible contingency event - QLD region - 24/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 24/04/2024

At 0855 hrs the Ross - Guybal Munjan 8916 275 kV line tripped at the Guybal Munjan end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.


Manager NEM Real Time Operations
     
116276POWER SYSTEM EVENTS23/04/2024 12:09:41 PM

Non-credible contingency event - VIC region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 23/04/2024

At 1056 hrs the MOPS 11 Gen TX 2 Bus 500kV CB and the Dundonnell WF tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.


Manager NEM Real Time Operations
     
116275INTER-REGIONAL TRANSFER23/04/2024 08:52:22 AM

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

At 0837 hrs 23/04/2024 there was an unplanned outage of Para No 1 SVC.

Constraint set(s) invoked: S-PA_VC1


This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116272INTER-REGIONAL TRANSFER22/04/2024 02:55:17 PM

Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.

The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024

Constraint set(s) revoked: N-LDTM_82_OPEN

Manager NEM Real Time Operations
     
116270INTER-REGIONAL TRANSFER22/04/2024 01:32:54 PM

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

At 1315 hrs 22/04/2024 there was an unplanned outage of Farrell - Sheffield Nos 1 and 2 220kV Lines.

The following constraint set(s) invoked at 1315 hrs 22/04/2024
T-X_FASH_C

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116209INTER-REGIONAL TRANSFER20/04/2024 12:10:41 AM

Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024

At 2341 hrs 19/04/2024 there was an unplanned outage of the Tailem Bend 275 kV Capacitor.

The following constraint set(s) invoked at 0005 hrs 20/04/2024
S-TBCP1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116208INTER-REGIONAL TRANSFER19/04/2024 05:09:45 PM

Inter-regional transfer limit variation - Murraylink interconnector - VIC and SA regions - 19/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Murraylink interconnector - VIC and SA regions - 19/04/2024

A planned outage of Murraylink interconnector was scheduled from 0800 hrs 24/03/2024 to 1700 hrs 27/04/2024.

The outage has been completed and Murraylink interconnector returned to service at 1710 hrs 19/04/2024

Constraint set(s) revoked: I-MURRAYLINK

This constraint set(s) contains equations with the following interconnectors on the LHS.

V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116196INTER-REGIONAL TRANSFER18/04/2024 07:05:27 PM

Inter-regional transfer limit variation - Tamworth No1 SVC Protection system- NSW region - 18/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No1 SVC Protection system - NSW region - 18/04/2024

At 1900 hrs 18/04/2024 there was a short notice outage of Tamworth No1 SVC protection system.

The following constraint set(s) invoked at 1900 hrs 18/04/2024
N-TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116162POWER SYSTEM EVENTS17/04/2024 06:10:18 AM

Update - Non-credible contingency event - VIC region - 17/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 17/04/2024

Refer AEMO Electricity Market Notice 116160

At 0610 hrs the Heywood No 2 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm