Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Monday, 18 June 2018
NON-CONFORMANCE QLD1 Region Monday, 18 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: SWAN_E
Duration: 18/06/2018 16:05 to 18/06/2018 16:10
Amount: 42 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 18 June 2018
NON-CONFORMANCE QLD1 Region Monday, 18 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: SWAN_E
Duration: 18/06/2018 11:00 to 18/06/2018 11:10
Amount: 45 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 18 June 2018
NON-CONFORMANCE QLD1 Region Monday, 18 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: TARONG#4
Duration: 18/06/2018 09:35 to 18/06/2018 09:40
Amount: 21 MW
Constraint: NC-Q_TARONG#4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 16 June 2018
NON-CONFORMANCE QLD1 Region Saturday, 16 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: MPP_2
Duration: 16/06/2018 15:35 to 16/06/2018 15:45
Amount: -15 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 16 June 2018
NON-CONFORMANCE VIC1 Region Saturday, 16 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: LYA2
Duration: 16/06/2018 11:55 to 16/06/2018 12:25
Amount: 70 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 June 2018
NON-CONFORMANCE QLD1 Region Thursday, 14 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: TARONG#1
Duration: 14/06/2018 18:05 to 14/06/2018 18:10
Amount: 76 MW
Constraint: NC-Q_TARONG#1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 14 June 2018
NON-CONFORMANCE NSW1 Region Thursday, 14 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: VP6
Duration: 14/06/2018 17:30 to 14/06/2018 17:40
Amount: -31 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 14 June 2018
NON-CONFORMANCE QLD1 Region Thursday, 14 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: TARONG#1
Duration: 14/06/2018 15:10 to 14/06/2018 15:20
Amount: -128 MW
Constraint: NC-Q_TARONG#1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 13 June 2018
NON-CONFORMANCE VIC1 Region Wednesday, 13 June 2018
AEMO declared a schedule generating unit non-conforming
Unit: MORTLK12
Duration: 13/06/2018 18:45 to 13/06/2018 18:50
Amount: -17 MW
Constraint: NC-V_MORTLK12
Auto-generated on behalf of Manager NEM Real Time Operations