Market Notices

115190RESERVE NOTICE27/02/2024 04:40:17 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115181 has been updated at 0440 hrs 27/02/2024 to the following:

[1.] From 1500 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 272 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
115183RESERVE NOTICE26/02/2024 09:48:57 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115153 has been updated at 2145 hrs 26/02/2024 to the following:

[1.] From 1700 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 373 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
115181RESERVE NOTICE26/02/2024 09:40:58 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115157 has been updated at 2140 hrs 26/02/2024 to the following:

[1.] From 1430 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1316 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
115157RESERVE NOTICE26/02/2024 05:34:52 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115135 has been updated at 1740 hrs 26/02/2024 to the following:

[1.] From 1430 hrs 29/02/2024 to 1930 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
115153RESERVE NOTICE26/02/2024 04:45:58 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 355 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
115135RESERVE NOTICE26/02/2024 02:14:06 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115132 has been updated at 1300 hrs 26/02/2024 to the following:

From 1630 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 324 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
115132RESERVE NOTICE26/02/2024 11:41:30 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115130 has been updated at 1100 hrs 26/02/2024 to the following:

From 1630 hrs to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 230 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
115130RESERVE NOTICE26/02/2024 10:04:05 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 678 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
115068RESERVE NOTICE24/02/2024 02:33:26 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115063 is cancelled at 0230 hrs 24/02/2024

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM RTO
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm